Permit Details

Permit Search

Permit

Roof Replacement or Repair

130 SW TREY WAY
LAKE CITY, FL 32024

Permit #
000053926
Application #
72833
Status Completed
  1. Submitted Aug 21, 2025
  2. Issued Aug 27, 2025
  3. Expires Mar 16, 2026
  4. Completed Sep 17, 2025

Property

Parcel #
02732-546
Owner
Anderson Wayne Harold, Anderson Maria Gertrude
Acres
0.50
Subdivision
Deer Creek Phase 3
Zoning
RSF/MH-3
Flood zone
X
District
3

Permit

Status
Completed
Septic release
N/A
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
Type Roofing Job
Replacement - Tear off Existing and Replace
Type of structure
House
Commercial or Residential
Residential
Roof Area (for this job) Sq Ft
23
No. of Stories
1
Roof Pitch
4:12 or Greater
Is the existing roof being removed?
Yes
Type of New Roofing Product
Asphalt Shingles
Florida Product Approval Number
FL18355-R5
Product Manufacturer
Tamko
Product Description
Asphalt Shingles
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Sealed roof decking options: (Must select an option.)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Ventilation:
Ridge Vent
Flashing:
Replace All
Drip Edge:
Replace All
Valley Treatment:
New Metal

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified.
  4. Point Review - Corrections Needed
  5. Final Review - Corrections Needed
  6. Final Review - Corrections Needed
  7. Application submitted by applicant.
  8. Final Review - Payment Needed
  9. Permit Issued
  10. Final Review - Complete

Contractors

  • Marc Boutilier

    Florida Premier Roofing Llc

    License
    CCC1333919
    Title
    Cert. Roofing
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Aug 29, 2025

    Rescheduled 9/2/2025:Re-Roof - In Progress

    Inspected by Troy Crews

  2. Sep 2, 2025

    Failed: Re-Roof - In Progress

    No Work Being Done

    Inspected by Troy Crews

  3. Sep 10, 2025

    Passed: Re-Roof - In Progress

    Inspected by Matt Forsyth

  4. Sep 16, 2025

    Passed: Re-Roof - Roof Affidavit Review

    Inspected by Matt Forsyth

  5. Sep 16, 2025

    Passed: Re-Roof - Roof Pictures Review

    Inspected by Matt Forsyth

  6. Sep 17, 2025

    Passed: Re-Roof - Final

    Inspected by Matt Forsyth