| 5/25/2025 |
Pending applicant completion and submission. |
| 5/25/2025 |
Final Review - Corrections Needed |
| 6/2/2025 |
Email confirmation reminder sent. |
| 6/2/2025 |
Email confirmation reminder sent. |
| 6/2/2025 |
Application submitted by applicant. |
| 6/2/2025 |
Pending Public Works Application Approval |
| 6/3/2025 |
Application Approved by Public Works |
| 6/3/2025 |
Final Review - Payment Needed |
| 6/5/2025 |
Final Review - Payment Needed |
| 6/9/2025 |
Final Review - Payment Needed |
| 6/10/2025 |
Final Review - Payment Needed |
| 6/11/2025 |
Final Review - Payment Needed |
| 6/16/2025 |
Final Review - Payment Needed |
| 6/17/2025 |
Final Review - Payment Needed |
| 6/18/2025 |
Final Review - Payment Needed |
| 6/20/2025 |
Final Review - Payment Needed |
| 6/21/2025 |
Final Review - Payment Needed |
| 6/23/2025 |
Pending initial driveway inspection |
| 6/23/2025 |
Final Review - Complete |
| 6/24/2025 |
Permit Issued |
| 6/24/2025 |
New address issued and ticket completed. |