Permit Details

Permit Search

Permit

New Residential Construction

3181 SW COUNTY ROAD 138
FORT WHITE, FL 32038

Permit #
000053393
Application #
71069
Status Completed
  1. Submitted May 19, 2025
  2. Issued Jun 18, 2025
  3. Expires Jul 15, 2026
  4. Completed Jan 20, 2026

Property

Parcel #
04298-021
Owner
Gainey Daniel Chase, Gainey Brooke Nicole
Acres
10.09
Subdivision
—
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Engineers Elevation Letter
Finished floor requirement
12" ABOVE ADJACENT GROUND FOR ENTIRE PERIMETER
Fema map number
12023C0531C
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
2660
Total Area (Sqft)
4724
Building Height
26
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
25-0410
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
400

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - On Hold-Incomplete
  4. Point Review - Printed-Online Application
  5. Point Review - Reviewed
  6. Zoning Review - Documents Required
  7. Plan Review - Documents Required
  8. Plan Review - Documents Required
  9. Plan Review - On Hold-Incomplete
  10. Plan Review - Building Approved
  11. Plan Review - Electrical Approved
  12. Plan Review - Mechanical Approved
  13. Plan Review - Plumbing Approved
  14. Plan Review - Fuel/Gas Approved
  15. Plan Review - Reviewed
  16. Zoning Review - Documents Required
  17. Zoning Review - Reviewed
  18. Final Review - Payment Needed
  19. Final Review - Complete
  20. Permit Issued
  21. Permit Status Update Notification

Contractors

This is an owner-builder project.

  • Robert M Bounds

    Bounds Heating & Air Inc

    License
    CAC057642
    Title
    Class A A/c
    Role
    Subcontractor
  • Chad J Opaleski

    Chad's Water Works Plumbing, Llc

    License
    CFC1427646
    Title
    Cert. Plumbing
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • William P Duffield

    Duffield Home Improvement

    License
    CCC1325785
    Title
    Roofing Contractor
    Role
    Subcontractor

Inspections

  1. Jun 20, 2025

    Failed: Plumbing/Gas - 1st Underground Rough–In

    Not Ready

    Inspected by Anthony Aslan

  2. Jun 24, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Anthony Aslan

  3. Jul 3, 2025

    Passed: Building - Monolithic Slab

    Inspected by Anthony Aslan

  4. Jul 3, 2025

    Passed: Engineering - Setbacks

    Appears Within The Setbacks

    Inspected by Anthony Aslan

  5. Jul 3, 2025

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Anthony Aslan

  6. Jul 9, 2025

    Passed: Electrical - Temporary Service

    Inspected by Anthony Aslan

  7. Jul 9, 2025

    Release to power company

    Inspected by Anthony Aslan

  8. Aug 1, 2025

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Anthony Aslan

  9. Aug 1, 2025

    Passed: Building - Roof Decking

    Inspected by Anthony Aslan

  10. Aug 1, 2025

    Cancelled: Building - Wall Sheathing

    Inspected by Anthony Aslan

  11. Aug 11, 2025

    Passed: Building - Framing

    Inspected by Anthony Aslan

  12. Aug 11, 2025

    Passed: Building - Window Attachment

    Inspected by Anthony Aslan

  13. Aug 28, 2025

    Cancelled: Mechanical - Above Ceiling

    Inspected by Anthony Aslan

  14. Aug 29, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Anthony Aslan

  15. Aug 29, 2025

    Passed: Mechanical - Rough In

    Inspected by Anthony Aslan

  16. Aug 29, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Anthony Aslan

  17. Sep 2, 2025

    Passed: Building - Insulation

    Spray Foam Attic, R-19 Walls And Floor

    Inspected by Anthony Aslan

  18. Oct 24, 2025

    Passed: Electrical - Permanent Power

    Need Septic Release

    Inspected by Anthony Aslan

  19. Nov 10, 2025

    Septic Release Inspection

    Inspected by Health Dept

  20. Nov 13, 2025

    Release to power company

    Rec'd Septic - Need Final Drive For Co

    Inspected by Ewilliams

  21. Nov 14, 2025

    Release to power company

    Inspected by Mgarber

  22. Jan 14, 2026

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  23. Jan 14, 2026

    Release to power company

    Inspected by Troy Crews

  24. Jan 14, 2026

    Passed: Building - Final

    Pending Elevation Confirmation Prior To Co-- 1.15.26 Mg

    Inspected by Troy Crews

  25. Jan 16, 2026

    Passed: Building - Spot Check

    Floor Pictures Emailed To Office

    Inspected by Troy Crews

Documents