| 5/19/2025 |
Application pending. |
| 5/19/2025 |
Application submitted by applicant. |
| 5/20/2025 |
Point Review - On Hold-Incomplete |
| 5/27/2025 |
Zoning Review - On Hold-Incomplete |
| 5/27/2025 |
Plan Review - On Hold-Incomplete |
| 5/30/2025 |
Point Review - Printed-Online Application |
| 5/30/2025 |
Point Review - Reviewed |
| 5/30/2025 |
Zoning Review - Reviewed |
| 6/2/2025 |
Plan Review - Electrical Approved |
| 6/2/2025 |
Plan Review - Building Approved |
| 6/2/2025 |
Plan Review - Reviewed |
| 6/2/2025 |
Final Review - Processing |
| 6/2/2025 |
Final Review - Payment Needed |
| 6/3/2025 |
Permit Issued |
| 6/3/2025 |
Final Review - Complete |