Permit Details

Permit Search

Permit

New Residential Construction

296 SE NATURE DR
LAKE CITY, FL 32025

Permit #
000053276
Application #
70569
Status Completed
  1. Submitted Apr 29, 2025
  2. Issued May 30, 2025
  3. Expires Jan 9, 2027
  4. Completed Sep 3, 2026

Property

Parcel #
08320-105
Owner
Neylon Margaret T, Neylon Francis X Jr
Acres
11.04
Subdivision
Eagles View Unr
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0315C
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
2
Heated Area (Sqft)
5280
Total Area (Sqft)
6675
Building Height
34.4
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
26-0447
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified.
  4. Zoning Review - Corrections Needed
  5. Point Review - Printed-Online Application
  6. Point Review - Reviewed
  7. Zoning Review - Corrections Needed
  8. Plan Review - Documents Required
  9. Plan Review - Building Approved
  10. Plan Review - Electrical Approved
  11. Plan Review - Mechanical Approved
  12. Plan Review - Plumbing Approved
  13. Plan Review - Fuel/Gas Approved
  14. Plan Review - Reviewed
  15. Zoning Review - Documents Required
  16. Zoning Review - Documents Required
  17. Zoning Review - Documents Required
  18. Zoning Review - Reviewed
  19. Final Review - Corrections Needed
  20. Final Review - Reviewed
  21. Final Review - Payment Needed
  22. Permit Issued
  23. Final Review - Complete

Contractors

  • Josh Sparks

    Sparks Construction

    License
    CBC1252260
    Title
    Building Contractor
    Role
    Contractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Ralph W Laverdure

    Rwl Roofing Llc

    License
    CCC1328590
    Title
    Roofing Contractor
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor
  • Benjamin L Sparks

    Line Electric Company Llc

    License
    EC13009101
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License Expired.

Inspections

  1. Jun 2, 2025

    Passed: Building - Footer

    Inspected by Anthony Aslan

  2. Jun 2, 2025

    Passed: Engineering - Setbacks

    Appears Within Setbacks

    Inspected by Anthony Aslan

  3. Jun 30, 2025

    Passed: Building - Lintel/Tie Beam

    Stem Wall

    Inspected by Anthony Aslan

  4. Jul 16, 2025

    Passed: Building - Slab

    Crawl Space

    Inspected by Anthony Aslan

  5. Sep 12, 2025

    Passed: Building - Roof Decking

    Inspected by Anthony Aslan

  6. Sep 12, 2025

    Passed: Building - Wall Sheathing

    Inspected by Anthony Aslan

  7. Sep 23, 2025

    Failed: Building - Framing

    Not Enough Detail On Plans, Need Engineer To Preform Framing Inspection

    Inspected by Anthony Aslan

  8. Dec 8, 2025

    Passed: Building - Framing

    Done By Architect Letter In File

    Inspected by Troy Crews

  9. Dec 9, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Christian Allen

  10. Dec 9, 2025

    Passed: Mechanical - Rough In

    Inspected by Christian Allen

  11. Dec 9, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Christian Allen

  12. Feb 3, 2026

    Passed: Building - Insulation

    Inspected by Christian Allen

  13. Feb 6, 2026

    Passed: Building - Window Attachment

    Inspected by Christian Allen

  14. Feb 6, 2026

    Passed: Building - Strapping

    Inspected by Christian Allen

  15. Feb 6, 2026

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Christian Allen

  16. Apr 17, 2026

    Passed: Electrical - Permanent Power

    Inspected by Christian Allen

  17. Jul 13, 2026

    Passed: Building - Final

    *final Septic Release Required Prior To Power Release & Co -- 8/17/26

    Inspected by Christian Allen

  18. Sep 3, 2026

    Septic Release Inspection

    Inspected by Health Dept

Documents