Permit Details

Permit Search

Permit

New Residential Construction

430 NW MULE WAY
LAKE CITY, FL 32055

Permit #
000053214
Application #
70300
Status Completed
  1. Submitted Apr 11, 2025
  2. Issued May 22, 2025
  3. Expires Jul 22, 2026
  4. Completed Jan 23, 2026

Property

Parcel #
01770-241
Owner
Mullins Lafarious, Mullins Thayla D
Acres
2.57
Subdivision
Country Lane Estates
Zoning
A-3
Flood zone
X
District
1

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0187D
This is the construction of a
Single Family Dwelling
Stories
1
Heated Area (Sqft)
2287
Total Area (Sqft)
2652
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
25-0147
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a minimum 4-inch wide strip of selfadhering polymer-modified bitumen complying with ASTM D1970 or a minimum 3 ¾ - inch wide strip of selfadhering flexible flashing tape complying with AAMA 711, applied over all joints in the roof decking. A felt underlayment complying with ASTM D226 Type II, ASTM D4869 Type Ill or IV, or ASTM D6757, or a synthetic underlayment meeting the performance requirements specified, is required to be applied over the strips/tape over the entire roof.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Processing
  4. Point Review - Printed-Online Application
  5. Plan Review - Documents Required
  6. Zoning Review - Processing
  7. Plan Review - Documents Required
  8. Zoning Review - On Hold-Incomplete
  9. Plan Review - Plumbing Approved
  10. Plan Review - Mechanical Approved
  11. Plan Review - Electrical Approved
  12. Plan Review - Building Approved
  13. Plan Review - Reviewed
  14. Zoning Review - Processing
  15. Zoning Review - Email Sent
  16. Zoning Review - Email Sent
  17. Zoning Review - Email Sent
  18. Zoning Review - Reviewed
  19. Final Review - Reviewed
  20. Final Review - Payment Needed
  21. Permit Issued
  22. Permit Status Update Notification

Contractors

  • Bryan Zecher

    Bryan Zecher Homes Inc

    License
    CBC1257343
    Title
    Building Contractor
    Role
    Contractor
  • Donald R Hollingsworth

    Holly Electric Inc

    License
    EC13005429
    Title
    Electrical
    Role
    Subcontractor
  • Anthony R Franks

    Lane Heating & Air Llc

    License
    CAC1818631
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    County License & State License Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Daniel Byrd

    Byrds Eye Roofing Inc

    License
    CCC1332899
    Title
    Cert. Roofing
    Role
    Subcontractor

Inspections

  1. Jun 2, 2025

    Passed: Building - Footer

    Put Ground Wire On Prior To Pour

    Inspected by Troy Crews

  2. Jun 2, 2025

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Jul 3, 2025

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  4. Jul 3, 2025

    Release to power company

    Inspected by Troy Crews

  5. Jul 28, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Waste Lines Only

    Inspected by Troy Crews

  6. Aug 11, 2025

    Passed: Building - Slab

    Inspected by Troy Crews

  7. Aug 28, 2025

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  8. Aug 28, 2025

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  9. Sep 17, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  10. Sep 17, 2025

    Failed: Electrical - 2nd Rough-In

    Need Nail Plate Over Service Entrance Cable At Top Plate

    Inspected by Troy Crews

  11. Sep 17, 2025

    Passed: Building - Framing

    Inspected by Troy Crews

  12. Sep 17, 2025

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  13. Sep 17, 2025

    Passed: Building - Strapping

    Call Electrical Back In With Insulation Inspection

    Inspected by Troy Crews

  14. Sep 26, 2025

    Passed: Electrical - 2nd Rough-In

    Nail Plates Installed

    Inspected by Troy Crews

  15. Sep 26, 2025

    Passed: Building - Insulation

    Inspected by Troy Crews

  16. Nov 12, 2025

    Cancelled: Engineering - D.O.T Final Driveway

    Inspected by Tcrews

  17. Nov 12, 2025

    Passed: Electrical - Permanent Power

    Septic Release Needed

    Inspected by Gary Pitzer

  18. Nov 26, 2025

    Release to power company

    Inspected by Mgarber

  19. Nov 26, 2025

    Septic Release Inspection

    Inspected by Health Dept

  20. Jan 23, 2026

    Passed: Building - Final

    Inspected by Troy Crews

Documents