Permit Details

Permit Search

Permit

New Residential Construction

6026 SW COUNTY ROAD 242
LAKE CITY, FL 32024

Permit #
000053162
Application #
70562
Status Completed
  1. Submitted Apr 29, 2025
  2. Issued May 20, 2025
  3. Expires Jul 5, 2026
  4. Completed Jan 13, 2026

Property

Parcel #
03245-004
Owner
Mowry Dale A, Mowry Whitney W
Acres
19.10
Subdivision
—
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0360C
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
2251
Total Area (Sqft)
3424
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
25-0040
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a minimum 4-inch wide strip of selfadhering polymer-modified bitumen complying with ASTM D1970 or a minimum 3 ¾ - inch wide strip of selfadhering flexible flashing tape complying with AAMA 711, applied over all joints in the roof decking. A felt underlayment complying with ASTM D226 Type II, ASTM D4869 Type Ill or IV, or ASTM D6757, or a synthetic underlayment meeting the performance requirements specified, is required to be applied over the strips/tape over the entire roof.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Point Review - Reviewed
  5. Zoning Review - Reviewed
  6. Plan Review - Documents Required
  7. Plan Review - Documents Required
  8. Plan Review - Documents Required
  9. Plan Review - Documents Required
  10. Plan Review - Plumbing Approved
  11. Plan Review - Mechanical Approved
  12. Plan Review - Electrical Approved
  13. Plan Review - Building Approved
  14. Plan Review - Reviewed
  15. Final Review - Processing
  16. Final Review - Processing
  17. Final Review - Reviewed
  18. Final Review - Payment Needed
  19. Permit Issued
  20. Permit Status Update Notification

Contractors

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Robert Ogles

    Ogles Roofing & Construction Llc

    License
    CCC1328699
    Title
    Cert Roofing
    Role
    Subcontractor

    County License & State License Expired.

  • Donald R Hollingsworth

    Holly Electric Inc

    License
    EC13005429
    Title
    Electrical
    Role
    Subcontractor
  • Anthony R Franks

    Lane Heating & Air Llc

    License
    CAC1818631
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    County License & State License Expired.

Inspections

  1. May 30, 2025

    Passed: Building - Footer

    Hook Bar From Footing 48 Inches Max Apart

    Inspected by Matt Forsyth

  2. May 30, 2025

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Jun 25, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Waste Pipe Inspected Electrical Conduit Under Slab Noted

    Inspected by Matt Forsyth

  4. Jul 3, 2025

    Passed: Building - Slab

    Nice Work

    Inspected by Matt Forsyth

  5. Aug 4, 2025

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Matt Forsyth

  6. Aug 4, 2025

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  7. Aug 4, 2025

    Passed: Building - Strapping

    Inspected by Matt Forsyth

  8. Aug 4, 2025

    Passed: Building - Wall Sheathing

    Inspected by Matt Forsyth

  9. Aug 29, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  10. Aug 29, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  11. Aug 29, 2025

    Passed: Mechanical - Above Ceiling

    Inspected by Matt Forsyth

  12. Aug 29, 2025

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  13. Sep 9, 2025

    Passed: Building - Insulation

    Walls And Ceiling

    Inspected by Matt Forsyth

  14. Sep 16, 2025

    Passed: Building - Lath/Stucco

    Inspected by Matt Forsyth

  15. Oct 29, 2025

    Passed: Electrical - Permanent Power

    Need Septic Release

    Inspected by Matt Forsyth

  16. Nov 5, 2025

    Release to power company

    Inspected by Ewilliams

  17. Nov 5, 2025

    Septic Release Inspection

    Inspected by Health Dept

  18. Jan 6, 2026

    Passed: Building - Final

    All Requirements Met To Release Co-- 1.13.25 Mg

    Inspected by Matt Forsyth

Documents