Permit Details

Permit Search

Permit

New Residential Construction

517 SW BUNN DR
LAKE CITY, FL 32024

Permit #
000053154
Application #
70935
Status Completed
  1. Submitted May 8, 2025
  2. Issued May 19, 2025
  3. Expires Dec 1, 2026
  4. Completed Jun 5, 2026

Property

Parcel #
08915-108
Owner
Raphael Richard, Swanson-raphael Althea R
Acres
5.40
Subdivision
Hawks Landing
Zoning
A-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
102.1'
Requirement needed
By Nailing Inspection
Document needed is
NA
Document receieved
No
Fema map number
12023C0382D
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
2
Heated Area (Sqft)
3328
Total Area (Sqft)
4658
Building Height
21
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
25-0384
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Zoning Review - Documents Required
  5. Zoning Review - Reviewed
  6. Plan Review - Documents Required
  7. Plan Review - Documents Required
  8. Point Review - Printed-Online Application
  9. Plan Review - Building Approved
  10. Plan Review - Electrical Approved
  11. Plan Review - Mechanical Approved
  12. Plan Review - Plumbing Approved
  13. Plan Review - Fuel/Gas Approved
  14. Plan Review - Reviewed
  15. Final Review - Reviewed
  16. Final Review - Payment Needed
  17. Permit Issued
  18. Point Review - Printed-Online Application

Contractors

  • Josh Sparks

    Sparks Construction

    License
    CBC1252260
    Title
    Building Contractor
    Role
    Contractor
  • Benjamin L Sparks

    Line Electric Company Llc

    License
    EC13009101
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License Expired.

  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Ralph W Laverdure

    Rwl Roofing Llc

    License
    CCC1328590
    Title
    Roofing Contractor
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Jun 6, 2025

    Passed: Engineering - Setbacks

    Inspected by Gary Pitzer

  2. Jun 6, 2025

    Passed: Building - Footer

    Inspected by Gary Pitzer

  3. Jul 11, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Dwv Only, No Water Lines, No Clean Out On Exterior

    Inspected by Gary Pitzer

  4. Jul 30, 2025

    Passed: Building - Slab

    Inspected by Anthony Aslan

  5. Aug 8, 2025

    Passed: Electrical - Temporary Service

    Inspected by Anthony Aslan

  6. Aug 8, 2025

    Release to power company

    Inspected by Anthony Aslan

  7. Aug 13, 2025

    Passed: Building - Lintel/Tie Beam

    Inspected by Anthony Aslan

  8. Oct 27, 2025

    Passed: Building - Framing

    Inspected by Gary Pitzer

  9. Oct 27, 2025

    Passed: Building - Strapping

    Inspected by Gary Pitzer

  10. Oct 27, 2025

    Passed: Building - Window Attachment

    Inspected by Gary Pitzer

  11. Oct 27, 2025

    Passed: Building - Roof Decking

    Inspected by Gary Pitzer

  12. Nov 21, 2025

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Gary Pitzer

  13. Nov 21, 2025

    Passed: Mechanical - Rough In

    Inspected by Gary Pitzer

  14. Nov 21, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Gary Pitzer

  15. Nov 21, 2025

    Failed: Electrical - 2nd Rough-In

    All Device Boxes Need Cut In And Wires Made Ready For Devices At Time Of Rough-in

    Inspected by Gary Pitzer

  16. Dec 4, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  17. Dec 12, 2025

    Passed: Building - Insulation

    R13 Walls Batts, Vaulted Ceiling R38 Batts

    Inspected by Gary Pitzer

  18. Apr 6, 2026

    Passed: Electrical - Permanent Power

    No Line Conductors

    Inspected by Gary Pitzer

  19. Apr 6, 2026

    Release to power company

    Inspected by Gary Pitzer

  20. Jun 4, 2026

    Passed: Building - Final

    *does Not Include Gas Inspection, Have Provider To Do Final Pressure Test And Start Up *all Requirements Met To Release Co-- 6.5.26 Mg

    Inspected by Troy Crews

  21. Jun 9, 2026

    Septic Release Inspection

    Inspected by Health Dept

Documents