New Residential Construction
Permit
| Application #: | 70218 |
| Permit #: |
000053081 |
| Related Permit: |
|
| Submitted: | Wednesday, April 2, 2025 |
| Issued: | Sunday, June 22, 2025 |
| Expires: | Tuesday, December 16, 2025 |
| Completed: | Tuesday, December 16, 2025 |
| Status: |
Completed |
| Septic Release? |
Yes |
Notes
*MFE = 117.3' PER ENGINEER LETTER, SURVEYOR TO CONFIRM FFE AND SETBACKS - ELEVATION CONFIRMATION REC'D AT 117.30', SETBACKS CONFIRMED
*DRIVE FINAL REQUIRED PRIOR TO POWER RELEASE
*CITY TAP INSPECTION REQUIRED PRIOR TO FINAL-- REQUEST THROUGH COUNTY
LAKE CITY UTLITY CUSTOMER SERVICE NOTES
04/16/25 The City of Lake City's Utility Department approved the tap application for water and sewer services. Locates must be obtained to ensure that the existing utility infrastructure is not damaged or obstructed.