Permit Details

Permit Search

Permit

Mobile Home

324 NE COLVIN AVE
LAKE CITY, FL 32055

Permit #
000052988
Application #
69887
Status Completed
  1. Submitted Mar 12, 2025
  2. Issued May 1, 2025
  3. Expires Dec 15, 2025
  4. Completed Jun 18, 2025

Property

Parcel #
04967-031
Owner
Davis Jay
Acres
1.03
Subdivision
Five Points Acres
Zoning
RSF/MH-2
Flood zone
X
District
1

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
Bottom of lowest beam must be one foot above the road
Fema map number
12023C0285D
Mobile Home is a:
Double Wide
Year Built
2021
Width (Ft.In)
28
Length (Ft.In)
56
Driveway access to home:
Existing Drive
Installation Decal #
104765
Septic #
25-0284
Setbacks Front
25'
Setback Side 1
10'
Setbacks Rear
15'
Dev Permit #
F023-
Setback Side 2
10'
Serial #
fl26100phbz02599ab
Wind Zone?
2
Residential or Commercial Use?
Residential
How many of bedrooms does this home have?
3
How many bathrooms does this home have?
2

Status & Review History

  1. City of Lake City Utilities Notified.
  2. Point Review - Reviewed
  3. Zoning Review - Documents Required
  4. Plan Review - Reviewed
  5. Zoning Review - Documents Required
  6. Zoning Review - Documents Required
  7. Zoning Review - Documents Required
  8. Zoning Review - On Hold-Incomplete
  9. Zoning Review - On Hold-Incomplete
  10. Zoning Review - On Hold-Incomplete
  11. Plan Review - Reviewed
  12. Zoning Review - Reviewed
  13. Final Review - Processing
  14. Final Review - Payment Needed
  15. Final Review - Payment Needed
  16. Permit Issued

Contractors

  • Brent M Strickland

    License
    IH1104218
    Title
    Mh Installer (ih)
    Role
    Contractor

Inspections

  1. Mar 13, 2025

    Passed: Mobile Home - In County Pre-Mobile Home before set-up

    Inspected by Troy Crews

  2. Jun 10, 2025

    Passed: Mobile Home - Mobile Home Set-Up Final

    Final Septic Release Required Prior To Release Of Power And Co-- 6.10.25 Mg

    Inspected by Anthony Aslan

  3. Jun 10, 2025

    Release to power company

    Final Septic Release Required Prior To Release Of Power And Co-- 6.15.25 Mg

    Inspected by Anthony Aslan

  4. Jun 10, 2025

    Passed: Engineering - Setbacks

    Appears Within Setbacks

    Inspected by Anthony Aslan

  5. Jun 18, 2025

    Passed: Certificate-Release Certificate

    Inspected by Anthony Aslan

  6. Jun 18, 2025

    Septic Release Inspection

    Inspected by Health Dept

  7. Jun 20, 2025

    Submitted Power Release through FPL Portal

    Inspected by Ward, Emaleigh C.