Permit Details

Permit Search

Permit

Communications Tower

4741 SW BIRLEY AVE
LAKE CITY, FL 32024

Permit #
000052777
Application #
69874
Status Completed
  1. Submitted Mar 11, 2025
  2. Issued Mar 31, 2025
  3. Expires Mar 23, 2026
  4. Completed Sep 24, 2025

Property

Parcel #
03077-008
Owner
Durrance William David Jr, Durrance Claire D
Acres
21.44
Subdivision
—
Zoning
RR
Flood zone
X
District
3

Permit

Status
Completed
Septic release
N/A
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
This is the construction of a:
T-Mobile collocation of new antennas and associated equipment onto an existing cell tower
Select access to property:
Existing Drive
Total Estimated Cost
24000
Tower Height
250
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Is this a new or existing tower?
Existing
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Point Review - Reviewed
  5. Zoning Review - Reviewed
  6. Plan Review - Documents Required
  7. Plan Review - Documents Required
  8. Plan Review - Documents Required
  9. Plan Review - Documents Required
  10. Plan Review - Documents Required
  11. Plan Review - Documents Required
  12. Plan Review - Documents Required
  13. Plan Review - Documents Required
  14. Plan Review - Documents Required
  15. Plan Review - Building Approved
  16. Plan Review - Reviewed
  17. Final Review - Payment Needed
  18. Permit Issued
  19. Final Review - Complete

Contractors

  • Gustavo N Dezzuto

    Sba Network Services Llc

    License
    CGC1524899
    Title
    Cert. General
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • George Wilcox

    Glw Electric Llc

    License
    EC13010419
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License & Liability Insurance & Employees Workers Comp Expired.

Inspections

  1. May 30, 2025

    Passed: Building - Footer

    Contractor Will Use Fiber Mesh Concrete

    Inspected by Matt Forsyth

  2. May 30, 2025

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Jun 3, 2025

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  4. Jun 3, 2025

    Cancelled: Electrical - Permanent Power

    Inspected by Troy Crews

  5. Jun 9, 2025

    Cancelled: Electrical - Permanent Power

    Inspected by Emaleigh Williams

  6. Jun 24, 2025

    Passed: Electrical - Permanent Power

    Second Meter

    Inspected by Troy Crews

  7. Jun 24, 2025

    Release to power company

    Inspected by Troy Crews

  8. Sep 24, 2025

    Passed: Certificate-Release Certificate

    Inspected by Crews, Malcolm T.