| 3/29/2024 |
Application pending. |
| 3/29/2024 |
Application submitted by applicant. |
| 3/29/2024 |
City of Lake City Utilities Notified. |
| 4/8/2024 |
Point Review - On Hold-Incomplete |
| 4/11/2024 |
Point Review - On Hold-Incomplete |
| 5/14/2024 |
Point Review - On Hold-Incomplete |
| 5/17/2024 |
Point Review - On Hold-Incomplete |
| 5/30/2024 |
Point Review - Printed-Online Application |
| 5/31/2024 |
Zoning Review - Documents Required |
| 7/10/2024 |
Zoning Review - Documents Required |
| 8/22/2024 |
Zoning Review - Documents Required |
| 10/1/2024 |
Zoning Review - Documents Required |
| 10/7/2024 |
Zoning Review - Documents Required |
| 10/7/2024 |
Point Review - Printed-Online Application |
| 11/4/2024 |
Zoning Review - Documents Required |
| 11/5/2024 |
Zoning Review - Documents Required |
| 12/3/2024 |
Zoning Review - Documents Required |
| 12/12/2024 |
Zoning Review - Documents Required |
| 1/6/2025 |
Zoning Review - Reviewed |
| 1/6/2025 |
Zoning Review - Reviewed |
| 1/6/2025 |
Plan Review - Documents Required |
| 1/6/2025 |
Plan Review - Plumbing Approved |
| 1/6/2025 |
Plan Review - Mechanical Approved |
| 1/6/2025 |
Plan Review - Electrical Approved |
| 1/6/2025 |
Plan Review - Building Approved |
| 1/6/2025 |
Plan Review - Reviewed |
| 1/6/2025 |
Final Review - Processing |
| 1/6/2025 |
Final Review - Reviewed |
| 1/6/2025 |
Final Review - Payment Needed |
| 1/7/2025 |
Permit Issued |
| 3/6/2025 |
Zoning Review - Documents Required |
| 3/6/2025 |
Zoning Review - Email Sent |
| 7/2/2025 |
Zoning Review - Reviewed |
| 11/19/2025 |
Permit Status Update Notification |
| 2/6/2026 |
Permit Status Update Notification |
| 2/26/2026 |
Permit Renewed |
| 2/26/2026 |
Permit Renewed |