Permit Details

Permit Search

Permit

Remodel

466 SW WINDSWEPT GLN
LAKE CITY, FL 32024

Permit #
000051913
Application #
67850
Status Completed
  1. Submitted Oct 30, 2024
  2. Issued Dec 20, 2024
  3. Expires Sep 9, 2025
  4. Completed Jul 1, 2025

Property

Parcel #
03120-705
Owner
Trafco Llc, Thomas Traficante
Acres
1.13
Subdivision
Windswept Industrial Unit 7
Zoning
ILW
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0381D
Type of Structure
Other
Commercial or Residential?
Commercial
Description of the work being performed:
offices and bathrooms
Dev Permit #
F023-
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Service Amps
400

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Processing
  4. Zoning Review - Reviewed
  5. Plan Review - Documents Required
  6. Plan Review - Documents Required
  7. Plan Review - Documents Required
  8. Plan Review - Documents Required
  9. Plan Review - Documents Required
  10. Plan Review - Documents Required
  11. Plan Review - Documents Required
  12. Point Review - Reviewed
  13. Plan Review - Documents Required
  14. Plan Review - Reviewed
  15. Final Review - Reviewed
  16. Final Review - Payment Needed
  17. Permit Issued
  18. Final Review - Payment Needed

Contractors

No contractors are listed on this permit.

Inspections

  1. Nov 5, 2024

    Passed: Fire - Plan Review

    Inspected by Cpt. Shane Overstreet

  2. Dec 23, 2024

    Passed: Electrical - Permanent Power

    Need Final Driveway Inspection For Release

    Inspected by Troy Crews

  3. Jan 9, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  4. Jan 9, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  5. Jan 16, 2025

    Cancelled: Engineering - Final Driveway

    Inspection Requested On Wrong Permit

    Inspected by Melissa Garber

  6. Jan 17, 2025

    Release to power company

    Tc Ok'd Per Chad Williams

    Inspected by Melissa Garber

  7. Feb 12, 2025

    Passed: Electrical - Above Ceiling

    Inspected by Troy Crews

  8. Feb 12, 2025

    Passed: Plumbing/Gas - Sanitary

    Inspected by Troy Crews

  9. Mar 13, 2025

    Passed: Building - Final

    Drive Constructed As Permitted, But The Outfall Of The Side Drain Has Some Erosion That Needs To Be Repaired-- Chad Spoke With Owner, Who Stated They Would Correct. Co Pending Final Ok From County Engineer-- 5.18.25 Mg-- Ok Per Chad-- 7.1.25 Mg

    Inspected by Troy Crews

Documents