Permit Details

Permit Search

Permit

New Residential Construction

351 SW CREWS FARM TER
LAKE CITY, FL 32025

Permit #
000051855
Application #
68223
Status Completed
  1. Submitted Nov 19, 2024
  2. Issued Jan 8, 2026
  3. Expires Aug 5, 2026
  4. Completed Feb 6, 2026

Property

Parcel #
08877-001
Owner
Camiel Timothy L, Camiel Sequeta J
Acres
7.01
Subdivision
—
Zoning
RSF-1
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0382D
This is the construction of a
Single Family Dwelling
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
15'
Stories
1
Heated Area (Sqft)
3355
Total Area (Sqft)
5107
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0845
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a self-adhering polymer-modified bitumen underlayment complying with ASTM D1970 applied over the entire roof.

Status & Review History

  1. City of Lake City Utilities Notified.
  2. Point Review - Received-Hard Copy Application
  3. Zoning Review - Corrections Needed
  4. Zoning Review - Corrections Needed
  5. Point Review - Reviewed
  6. Zoning Review - Reviewed
  7. Plan Review - Documents Required
  8. Plan Review - Building Approved
  9. Plan Review - Electrical Approved
  10. Plan Review - Mechanical Approved
  11. Plan Review - Plumbing Approved
  12. Plan Review - Fuel/Gas Approved
  13. Plan Review - Reviewed
  14. Final Review - Documents Required
  15. Final Review - Payment Needed
  16. Final Review - Payment Needed
  17. Permit Issued
  18. Permit Reissued
  19. Permit Renewed

Contractors

  • Anthony George,jr.

    George Construction Llc

    License
    CGC016583
    Title
    General Contractor
    Role
    Contractor

    Workers Comp Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Robert Lynch

    Third Day Electric Llc

    License
    EC13001947
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License Expired.

  • Lonnie T Bucchi

    Ace Heat & Air Inc

    License
    CAC1817024
    Title
    Cert Ac Class A
    Role
    Subcontractor

Inspections

  1. Feb 17, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Dwv Only, No Clean Out

    Inspected by Gary Pitzer

  2. Feb 24, 2025

    Cancelled: Building - Slab

    Inspected by Melissa Garber

  3. Feb 25, 2025

    Passed: Building - Slab

    Plastic And Taped, Electric Conduits For Future Use And Floor Outlets

    Inspected by Gary Pitzer

  4. Feb 25, 2025

    Passed: Engineering - Setbacks

    In Large Field

    Inspected by Gary Pitzer

  5. Feb 25, 2025

    Passed: Building - Footer

    2#5 Rebar On Chairs, Please Post Address At First Gate

    Inspected by Gary Pitzer

  6. Apr 15, 2025

    Cancelled: Re-Roof - In Progress

    Inspected by Gary Pitzer

  7. Apr 15, 2025

    Passed: Building - Roof Decking

    Inspected by Gary Pitzer

  8. Apr 15, 2025

    Passed: Building - Wall Sheathing

    Inspected by Gary Pitzer

  9. Apr 25, 2025

    Passed: Electrical - Temporary Service

    60 Amp Temp. Service With Well Power And 1 Gfci Outlet

    Inspected by Gary Pitzer

  10. Apr 25, 2025

    Release to power company

    Inspected by Gary Pitzer

  11. May 14, 2025

    Failed: Plumbing/Gas - 2nd Rough-In

    1. Proper Protection Plates For Flex Gas Line, 2. Air Test On Gas Line, 3. Seal Around Water Line Where The Line Enters In Foundation

    Inspected by Gary Pitzer

  12. May 14, 2025

    Failed: Electrical - 2nd Rough-In

    Exhaust Fans Not Wired

    Inspected by Gary Pitzer

  13. May 21, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  14. May 21, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Check Pipe Entry Next Inspection

    Inspected by Gary Pitzer

  15. Jul 30, 2025

    Passed: Building - Insulation

    Walls R-13 Batt, Attic Spray Foam

    Inspected by Anthony Aslan

  16. Jan 14, 2026

    Passed: Building - Spot Check

    Permanent Power Coming Soon

    Inspected by Troy Crews

  17. Jan 30, 2026

    Passed: Electrical - Permanent Power

    Need Final Septic

    Inspected by Troy Crews

  18. Jan 30, 2026

    Release to power company

    Inspected by Troy Crews

  19. Feb 5, 2026

    Septic Release Inspection

    Inspected by Health Dept

  20. Feb 6, 2026

    Passed: Building - Final

    Need Blower Door Test For Release Any Gas Appliances Should Be Started Up By Gas Supplier

    Inspected by Troy Crews

  21. Feb 6, 2026

    Passed: Certificate - Release Certificate

    Blower Door Recieved

    Inspected by Crews, Malcolm T.