Permit Details

Permit Search

Permit

New Residential Construction

837 SW MEADOWLANDS DR
LAKE CITY, FL 32024

Permit #
000051582
Application #
67142
Status Completed
  1. Submitted Oct 14, 2024
  2. Issued Nov 21, 2024
  3. Expires Jul 25, 2026
  4. Completed Jan 26, 2026

Property

Parcel #
09617-218
Owner
Anderson Richard A, Anderson Jeri K
Acres
4.97
Subdivision
Meadowlands Phase 2
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Engineers Elevation Letter
Finished floor requirement
12" above adjacent ground for entire perimeter
Fema map number
12023C0485C
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
1900
Total Area (Sqft)
5000
Building Height
22
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0730
If Other, explain the use of the structure.
Single Family Residence, "barndominium" with spray foam insulation
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
Other (explain)
Sealed roof decking explanation for other option.
part of metal building
Service Amps
400

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - On Hold-Incomplete
  4. Point Review - Printed-Online Application
  5. Plan Review - Corrections Needed
  6. Plan Review - Building Approved
  7. Plan Review - Electrical Approved
  8. Plan Review - Mechanical Approved
  9. Plan Review - Plumbing Approved
  10. Plan Review - Fuel/Gas Approved
  11. Plan Review - Reviewed
  12. Zoning Review - Reviewed
  13. Final Review - Corrections Needed
  14. Point Review - Printed-Online Application
  15. Final Review - Reviewed
  16. Final Review - Payment Needed
  17. Permit Issued
  18. Final Review - Complete
  19. Permit Status Update Notification

Contractors

This is an owner-builder project.

  • Matthew Green

    Greens Sales & Services 2 Inc

    License
    CAC1820394
    Title
    Cert. A/c Class “b”
    Role
    Contractor

Inspections

  1. Dec 17, 2024

    Passed: Electrical - 1st Underground Rough–In

    Under Slab

    Inspected by Gary Pitzer

  2. Dec 17, 2024

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Water Pressurized, Dwv With Cleanout

    Inspected by Gary Pitzer

  3. Dec 19, 2024

    Passed: Engineering - Setbacks

    Inspected by Gary Pitzer

  4. Dec 19, 2024

    Passed: Building - Monolithic Slab

    2 Main Slab

    Inspected by Gary Pitzer

  5. Jan 3, 2025

    Passed: Building - Monolithic Slab

    Inspected by Gary Pitzer

  6. Jan 3, 2025

    Passed: Engineering - Setbacks

    Inspected by Gary Pitzer

  7. Feb 12, 2025

    Passed: Building - Framing

    Metal Framing For Shell Only

    Inspected by Gary Pitzer

  8. Feb 20, 2025

    Passed: Electrical - Temporary Service

    Temp Electric Only, One Outlet Only On Exterior

    Inspected by Gary Pitzer

  9. Feb 20, 2025

    Release to power company

    Inspected by Gary Pitzer

  10. Mar 3, 2025

    Septic Release Inspection

    Inspected by Health Dept

  11. Jun 10, 2025

    Failed: Building - Framing

    Need Draft Stopping Around Perimeter Of Walls

    Inspected by Gary Pitzer

  12. Jun 10, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Gary Pitzer

  13. Jun 10, 2025

    Failed: Mechanical - Rough In

    All Boxes Need Pads

    Inspected by Gary Pitzer

  14. Jun 10, 2025

    Failed: Electrical - 2nd Rough-In

    1, Need Underground Cable In Kitchen And Out Of J Box To Camper Plug, 2. Cover Underground Feeder Cable With Some Type Of Conduit Under Sub Panel, 3. Secure Nonmetallic Wiring In Several Location In Walls, 4. Terminate All Wire In Boxes And Have Made Ready For Devices

    Inspected by Gary Pitzer

  15. Jul 2, 2025

    Passed: Mechanical - Rough In

    Inspected by Gary Pitzer

  16. Jul 2, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  17. Jul 2, 2025

    Passed: Building - Framing

    Inspected by Gary Pitzer

  18. Dec 8, 2025

    Passed: Electrical - Permanent Power

    Four Wire Was Added To Sub-panel To Clear Up Defect

    Inspected by Gary Pitzer

  19. Dec 10, 2025

    Release to power company

    Inspected by Gary Pitzer

  20. Jan 23, 2026

    Passed: Building - Final

    Inspected by Troy Crews

  21. Jan 26, 2026

    Passed: Certificate - Release Certificate

    Placed Pictures In File 12 Inch Above Existing Grade

    Inspected by Crews, Malcolm T.

Documents