Solar Power System
Permit
| Application #: | 66192 |
| Permit #: |
000051211 |
| Related Permit: |
|
| Submitted: | Thursday, July 11, 2024 |
| Issued: | Wednesday, October 23, 2024 |
| Expires: | Monday, April 21, 2025 |
| Completed: | Monday, April 21, 2025 |
| Status: |
Completed |
| Septic Release? |
N/A |
Job Details
| Elevation regulation |
None |
| Finished floor requirement |
|
| Fema map number |
12023C0395C |
| PV Type |
Stand Alone PV System with Batteries- (DC system) separate electric permit not required. |
| Grounding |
N.E.C. Chapter 690 |
| AC Options |
USE-2;UF |
| AC Options (Cont..) |
In Conduit;THWN-2 |
| Building Code Edition |
2023 Florida Building Code 8th Edition and 2020 National Electrical Code |
| Power Company |
Clay Electric |
| Residential or Commercial? |
Residential |
| Setbacks Front |
30' |
| Setback Side 1 |
25' |
| Setbacks Side 2 |
25' |
| Setbacks Rear |
25' |
| Where are the panels mounted? |
Ground Mounted |
| Service Amps |
200 |
Review Notes
| 7/11/2024 |
Application pending. |
| 7/11/2024 |
Application submitted by applicant. |
| 7/11/2024 |
Point Review - Printed-Online Application |
| 7/12/2024 |
Zoning Review - Reviewed |
| 7/16/2024 |
Plan Review - Reviewed |
| 7/26/2024 |
Final Review - Processing |
| 8/26/2024 |
Final Review - Corrections Needed |
| 8/27/2024 |
Final Review - Corrections Needed |
| 9/3/2024 |
Final Review - Corrections Needed |
| 9/11/2024 |
Final Review - Corrections Needed |
| 9/11/2024 |
Final Review - Corrections Needed |
| 10/18/2024 |
Final Review - Reviewed |
| 10/18/2024 |
Final Review - Payment Needed |
| 10/21/2024 |
Final Review - Payment Needed |
| 10/23/2024 |
Permit Issued |
| 4/21/2025 |
Application Voided |
Contractors
| Name / Business |
License |
Title |
Role |
Joseph B Lane Joseph B Lane
Liability Insurance Expired. |
CVC57190 |
Cert. Solar |
Contractor |
Mark Derringer Bob Heinmiller Air Conditioning Inc
Liability Insurance & Workers Comp Expired. |
EC0001898 |
Cert. Electrical |
Subcontractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Failed: Solar - Solar Final |
1. No Exterior Disconnect , 2. Not Any Working Clearances In Front Of Interior Equipment, 3. Need Engineer Report For Footer Poured Without Inspection. Please Post Address At Site Per Unit At Site |
Gary Pitzer |
10/30/2024 |