Permit Details

Permit Search

Permit

Additions

320 SW AINSLEY GLN
LAKE CITY, FL 32024

Permit #
000050887
Application #
65762
Status Completed
  1. Submitted Jul 17, 2024
  2. Issued Sep 23, 2024
  3. Expires Feb 21, 2026
  4. Completed Aug 25, 2025

Property

Parcel #
03405-214
Owner
Handy Jonathan Michael, Handy Stacy Sue
Acres
1.00
Subdivision
Southwood Meadows Unit 2
Zoning
A-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
Meet existing structure
Fema map number
12023C0383D
Description of addition:
Dining Area expansion
Select driveway access to property:
Existing Drive
Fire sprinklers?
No
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setback Rear
25'
Stories
1
Heated Area (Sqft)
156
Total Area (Sqft)
156
Total Estimated Cost
20000
Building Height
8
Dev Permit #
F023-
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic#
24-0572
Is this an addition for commercial or residential use?
Residential
Sealed roof decking options. (Must select one.)
Other (explain)
Sealed roof decking explanation for other option.
Roofing is going to be done in conjunction with a reroof of the entire house that will be permitted separately
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Zoning Review - Reviewed
  5. Plan Review - Documents Required
  6. Plan Review - Reviewed
  7. Final Review - Payment Needed
  8. Permit Issued

Contractors

This is an owner-builder project.

Inspections

  1. Sep 4, 2024

    Septic Release Inspection

    Inspected by Health Dept

  2. Oct 31, 2024

    Passed: Engineering - Setbacks

    Attached To Rear Of Existing Home, Appears To Meet Setbacks

    Inspected by Gary Pitzer

  3. Oct 31, 2024

    Passed: Building - Monolithic Slab

    Mono Footer With 2#5 Rebar Wired And Wire For Slab, Plastic With Tap

    Inspected by Gary Pitzer

  4. Nov 27, 2024

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  5. Dec 26, 2024

    Passed: Building - Framing

    Inspected by Gary Pitzer

  6. Dec 26, 2024

    Passed: Building - Strapping

    Inspected by Gary Pitzer

  7. Dec 26, 2024

    Passed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  8. Dec 30, 2024

    Passed: Building - Insulation

    Inspected by Gary Pitzer

  9. Aug 25, 2025

    Passed: Certificate-Release Certificate

    Inspected by Troy Crews

  10. Aug 25, 2025

    Passed: Building - Final

    All Requirements Met To Release Co-- 8.25.25 Mg

    Inspected by Troy Crews

Documents