| 11/1/2023 |
Application pending. |
| 11/29/2023 |
Application submitted by applicant. |
| 12/1/2023 |
Point Review - On Hold-Incomplete |
| 1/26/2024 |
Point Review - Printed-Online Application |
| 1/26/2024 |
Point Review - Reviewed |
| 1/30/2024 |
Plan Review - Corrections Needed |
| 2/5/2024 |
Plan Review - On Hold-Incomplete |
| 2/5/2024 |
Plan Review - On Hold-Incomplete |
| 2/12/2024 |
Plan Review - On Hold-Incomplete |
| 2/15/2024 |
Plan Review - Building Approved |
| 2/15/2024 |
Plan Review - Electrical Approved |
| 2/15/2024 |
Plan Review - Mechanical Approved |
| 2/15/2024 |
Plan Review - Plumbing Approved |
| 2/15/2024 |
Plan Review - Fuel/Gas Approved |
| 2/15/2024 |
Plan Review - Reviewed |
| 2/26/2024 |
Plan Review - Documents Required |
| 3/19/2024 |
Plan Review - Documents Required |
| 3/22/2024 |
Plan Review - Documents Required |
| 4/3/2024 |
Plan Review - Plumbing Approved |
| 4/3/2024 |
Plan Review - Mechanical Approved |
| 4/3/2024 |
Plan Review - Electrical Approved |
| 4/3/2024 |
Plan Review - Building Approved |
| 4/3/2024 |
Plan Review - Reviewed |
| 4/23/2024 |
Zoning Review - Reviewed |
| 4/23/2024 |
Final Review - Processing |
| 4/29/2024 |
Final Review - Processing |
| 4/30/2024 |
Final Review - Documents Required |
| 5/17/2024 |
Final Review - Documents Required |
| 6/5/2024 |
Final Review - Documents Required |
| 6/10/2024 |
Final Review - Documents Required |
| 7/10/2024 |
Final Review - Documents Required |
| 8/16/2024 |
Final Review - Documents Required |
| 8/27/2024 |
Zoning Review - Reviewed |
| 8/27/2024 |
Final Review - Payment Needed |
| 8/29/2024 |
Permit Issued |
| 12/31/2024 |
Point Review - Reviewed |