| Passed: Engineering - Setbacks |
Appears With Setbacks On Site Plan |
Gary Pitzer |
8/20/2024 |
| Passed: Building - Footer |
2 #5 Rebar With Uprights For Stem Walls, All Wired |
Gary Pitzer |
8/20/2024 |
| Passed: Electrical - 1st Underground Rough–In |
Under Slab Conduits |
Gary Pitzer |
9/24/2024 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Dwv Only, No Clean Out On Exterior |
Gary Pitzer |
9/24/2024 |
| Failed: Building - Slab |
Slab Not Ready For Inspection |
Gary Pitzer |
10/1/2024 |
| Passed: Building - Slab |
Perimeter Steel Wired, Plastic Taped, Contractor Using Fiber Crete, I Asked For Copies Of Load Tickets |
Gary Pitzer |
10/2/2024 |
| Passed: Building - Wall Sheathing |
|
Gary Pitzer |
11/7/2024 |
| Passed: Building - Roof Decking |
Partial Is Second Floor Area, Lower Roof Remains Not Completd |
Gary Pitzer |
12/4/2024 |
| Passed: Building - Roof Decking |
|
Gary Pitzer |
12/20/2024 |
| Passed: Building - Framing |
|
Gary Pitzer |
1/7/2025 |
| Passed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
4/9/2025 |
| Passed: Mechanical - Rough In |
|
Gary Pitzer |
4/9/2025 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Gary Pitzer |
4/9/2025 |
| Passed: Building - Insulation |
|
All Batts, Walls And Ceilings |
5/23/2025 |
| Passed: Electrical - Permanent Power |
Need Septic Release |
Matt Forsyth |
8/5/2025 |
| Release to power company |
Rec'd Septic - Ew |
Ewilliams |
8/14/2025 |
| Septic Release Inspection |
|
Health Dept |
8/14/2025 |
| Passed: Building - Spot Check |
|
Troy Crews |
2/3/2026 |
| Passed: Building - Final |
|
Gary Pitzer |
4/16/2026 |