Permit Details

Permit Search

Permit

New Residential Construction

151 SW KAYLA CT
FORT WHITE, FL 32038

Permit #
000050346
Application #
65497
Status Completed
  1. Submitted May 28, 2024
  2. Issued Jul 12, 2024
  3. Expires Apr 21, 2025
  4. Completed Dec 18, 2024

Property

Parcel #
04184-004
Owner
Klemans R W
Acres
10.30
Subdivision
Glenn Farms Unr
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0495C
This is the construction of a
Single Family Dwelling
Stories
1
Heated Area (Sqft)
1572
Total Area (Sqft)
2078
Building Height
17
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0216
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.

Status & Review History

  1. Application pending.
  2. Point Review - Printed-Online Application
  3. Point Review - Reviewed
  4. Zoning Review - Reviewed
  5. Plan Review - Reviewed
  6. Final Review - Documents Required
  7. Final Review - Documents Required
  8. Final Review - Documents Required
  9. Final Review - Documents Required
  10. Final Review - Documents Required
  11. Final Review - Documents Required
  12. Final Review - Reviewed
  13. Final Review - Payment Needed
  14. Permit Issued
  15. Final Review - Payment Needed

Contractors

This is an owner-builder project.

Inspections

  1. Jul 11, 2024

    Septic Release Inspection

    Inspected by Health Dept

  2. Jul 15, 2024

    Passed: Electrical - Permanent Power

    Need C/o's Paid

    Inspected by Anthony Aslan

  3. Aug 14, 2024

    Release to power company

    C/o Payment Re'cved

    Inspected by Anthony Aslan

  4. Oct 23, 2024

    Passed: Building - Final

    Need Blower Door final Termite

    Inspected by Anthony Aslan

  5. Dec 18, 2024

    Certificate-Release Certificate

    Documents Received

    Inspected by Anthony Aslan

Documents