| 4/15/2024 |
Application pending. |
| 5/6/2024 |
Application submitted by applicant. |
| 5/9/2024 |
Point Review - On Hold-Incomplete |
| 5/9/2024 |
Point Review - On Hold-Incomplete |
| 6/5/2024 |
Point Review - Printed-Online Application |
| 6/6/2024 |
Zoning Review - Reviewed |
| 6/12/2024 |
Plan Review - Reviewed |
| 6/20/2024 |
Final Review - Corrections Needed |
| 6/25/2024 |
Final Review - Corrections Needed |
| 7/2/2024 |
Final Review - Reviewed |
| 7/2/2024 |
Final Review - Payment Needed |
| 7/2/2024 |
Final Review - Documents Required |
| 7/10/2024 |
Final Review - Documents Required |
| 7/11/2024 |
Permit Issued |