| Passed: Building - Footer |
Footing Needs To Dry Out |
Matt Forsyth |
7/31/2024 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
7/31/2024 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Water Supply Under Slab Under Pressure |
Matt Forsyth |
8/23/2024 |
| Electrical -Temporary Service |
|
Matt Forsyth |
9/18/2024 |
| Passed: Building - Slab |
|
Matt Forsyth |
9/18/2024 |
| Passed: Electrical - Temporary Service |
Waiting For Pictures Of Romex Removed From Panel Hanging Out |
Matt Forsyth |
9/18/2024 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
10/29/2024 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
10/29/2024 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
1/13/2025 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
1/13/2025 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
1/13/2025 |
| Passed: Building - Framing |
Garage Door And One Window Will Complete The Envelope |
Matt Forsyth |
1/14/2025 |
| Passed: Building - Insulation |
Spray Foam Attic Later Date |
Matt Forsyth |
1/21/2025 |
| Septic Release Inspection |
|
Health Dept |
3/14/2025 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
3/20/2025 |
| Release to power company |
Driveway Final Required Prior To Release Of Power To Fpl-- 3.28.25 (rec'd) |
Matt Forsyth |
3/21/2025 |
| Submitted Power Release through FPL Portal |
|
Garber, Melissa |
4/1/2025 |
| Passed: Building - Final |
Documents Pending |
Matt Forsyth |
5/14/2025 |
| Certificate-Release Certificate |
Rec'd Blower Door And Termite |
Matt Forsyth |
5/15/2025 |