| Application #: | 64945 |
| Permit #: |
000050312 |
| Related Permit: |
|
| Submitted: | Wednesday, April 17, 2024 |
| Issued: | Tuesday, July 9, 2024 |
| Expires: | Thursday, March 6, 2025 |
| Completed: | Thursday, March 6, 2025 |
| Status: |
Completed |
| Septic Release? |
Yes |
| Finished floor requirement |
|
| Fema map number |
12023C0508C |
| Type of Structure |
House |
| Commercial or Residential? |
Residential |
| Description of the work being performed: |
16 Replacement Windows |
| Dev Permit # |
F023- |
| Building Code Edition |
Florida Building Code 2017 6th Edition & 2014 National Electrical Code |
| 4/17/2024 |
Application pending. |
| 4/17/2024 |
Application submitted by applicant. |
| 4/18/2024 |
Point Review - Printed-Online Application |
| 4/18/2024 |
Zoning Review - On Hold-Incomplete |
| 4/26/2024 |
Zoning Review - Documents Required |
| 5/14/2024 |
Zoning Review - Documents Required |
| 6/4/2024 |
Zoning Review - Reviewed |
| 6/7/2024 |
Plan Review - Plumbing Approved |
| 6/7/2024 |
Plan Review - Mechanical Approved |
| 6/7/2024 |
Plan Review - Electrical Approved |
| 6/7/2024 |
Plan Review - Building Approved |
| 6/7/2024 |
Plan Review - Reviewed |
| 6/7/2024 |
Final Review - Processing |
| 6/10/2024 |
Final Review - Documents Required |
| 6/17/2024 |
Final Review - Documents Required |
| 6/25/2024 |
Final Review - Documents Required |
| 7/1/2024 |
Final Review - Documents Required |
| 7/2/2024 |
Final Review - Documents Required |
| 7/5/2024 |
Final Review - Corrections Needed |
| 7/9/2024 |
Final Review - Reviewed |
| 7/9/2024 |
Final Review - Payment Needed |
| 7/9/2024 |
Permit Issued |
| Name / Business |
License |
Title |
Role |
John G Oneal Oneal Contracting Inc
|
CGC1504135 |
Cert. General |
Contractor |
David P Wood Woods Electrical Services Inc
|
EC13002213 |
Electrical Contractor |
Subcontractor |
Mark Dawson Paradise Plumbing Services, Llc.
County License & State License & Liability Insurance & Workers Comp Expired. |
CFC1427245 |
Plumbing Contractor |
Subcontractor |
| Inspection |
Notes |
Performed By |
Date |
| Septic Release Inspection |
|
Health Dept |
7/3/2024 |
| Passed: Building - Framing |
|
Troy Crews |
11/18/2024 |
| Passed: Building - Roof Decking |
|
Troy Crews |
11/18/2024 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
11/18/2024 |
| Passed: Building - Monolithic Slab |
|
Troy Crews |
11/19/2024 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
11/19/2024 |
| Passed: Building - Framing |
|
Troy Crews |
12/11/2024 |
| Passed: Building - Insulation |
|
Troy Crews |
12/11/2024 |
| Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
12/11/2024 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
12/11/2024 |
| Certificate-Release Certificate |
|
Troy Crews |
3/6/2025 |
| Passed: Building - Final |
Cannot Closed Permit Or Release Certificate Of Occupancy Due To Missing Required Documents. |
Troy Crews |
3/6/2025 |