| 3/22/2024 |
Application pending. |
| 3/28/2024 |
Application submitted by applicant. |
| 4/9/2024 |
Point Review - Printed-Online Application |
| 4/10/2024 |
Zoning Review - Reviewed |
| 4/12/2024 |
Plan Review - Documents Required |
| 4/15/2024 |
Plan Review - Building Approved |
| 4/15/2024 |
Plan Review - Electrical Approved |
| 4/15/2024 |
Plan Review - Mechanical Approved |
| 4/15/2024 |
Plan Review - Plumbing Approved |
| 4/15/2024 |
Plan Review - Fuel/Gas Approved |
| 4/15/2024 |
Plan Review - Reviewed |
| 5/20/2024 |
Final Review - Processing |
| 5/22/2024 |
Final Review - Reviewed |
| 5/22/2024 |
Final Review - Payment Needed |
| 5/31/2024 |
Final Review - Payment Needed |
| 6/5/2024 |
Final Review - Payment Needed |
| 6/11/2024 |
Final Review - Payment Needed |
| 6/17/2024 |
Final Review - Payment Needed |
| 6/20/2024 |
Final Review - Payment Needed |
| 6/24/2024 |
Final Review - Payment Needed |
| 6/28/2024 |
Final Review - Payment Needed |
| 7/1/2024 |
Final Review - Payment Needed |
| 7/1/2024 |
Permit Issued |