Permit Details

Permit Search

Permit

New Residential Construction

301 NW COLEMAN PL
LAKE CITY, FL 32055

Permit #
000049820
Application #
64751
Status Completed
  1. Submitted Apr 1, 2024
  2. Issued May 15, 2024
  3. Expires Mar 5, 2025
  4. Completed Sep 11, 2024

Property

Parcel #
01890-120
Owner
Jorge Yasmamis Reyers,
Acres
2.58
Subdivision
Woods At Falling Creek
Zoning
PRRD
Flood zone
X
District
1

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Elevation regulation
Subdivision Plat
Finished floor requirement
142'
Requirement needed
By Nailing Inspection
Document needed is
a Surveyor letter giving the Finished Floor Elevation
Document receieved
Yes
Fema map number
12023C0195D
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
1502
Total Area (Sqft)
1803
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0324
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.

Status & Review History

  1. Point Review - Printed-Online Application
  2. Zoning Review - Reviewed
  3. Plan Review - Building Approved
  4. Plan Review - Electrical Approved
  5. Plan Review - Mechanical Approved
  6. Plan Review - Plumbing Approved
  7. Plan Review - Fuel/Gas Approved
  8. Plan Review - Reviewed
  9. Final Review - Documents Required
  10. Final Review - Reviewed
  11. Final Review - Payment Needed
  12. Final Review - Payment Needed
  13. Permit Issued
  14. Final Review - Payment Needed

Contractors

  • Maday L Diaz

    Diaz Homes & Construction Corp

    License
    CRC 1332651
    Title
    Cert. General
    Role
    Contractor

    County License & State License & Liability Insurance & Employees Workers Comp Expired.

  • Yordan Carrazana

    Best Lighting Electric

    License
    EC13007882
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License & Liability Insurance Expired.

  • Albert Heal

    All 4 Constrction Corp

    License
    CMC1249873
    Title
    Cert. Mechanical
    Role
    Subcontractor

    County License & State License & Liability Insurance Expired.

  • Albert Heal

    All 4 Construction Corp

    License
    CFC1428037
    Title
    Cert. Plumbing
    Role
    Subcontractor

    County License & State License & Liability Insurance Expired.

Inspections

  1. May 16, 2024

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Dwv Under Slab, No Clean Out On Exterior, One Set Of Water Under Slab No Test On (washer To Kitchen Wall)

    Inspected by Gary Pitzer

  2. May 22, 2024

    Electrical -1st Underground Rough–In

    Bonding Wire To Steel

    Inspected by Gary Pitzer

  3. May 22, 2024

    Passed: Building - Footer

    2#5 Bars Wired And On Chairs

    Inspected by Gary Pitzer

  4. May 22, 2024

    Passed: Engineering - Setbacks

    Inspected by Gary Pitzer

  5. Jun 12, 2024

    Failed: Building - Vertical Cells/Columns

    Not Complete

    Inspected by Anthony Aslan

  6. Jun 13, 2024

    Passed: Building - Lintel/Tie Beam

    Inspected by Troy Crews

  7. Jun 13, 2024

    Passed: Building - Vertical Cells/Columns

    Inspected by Troy Crews

  8. Jun 13, 2024

    Cancelled: Building - Strapping

    Inspected by Troy Crews

  9. Jun 24, 2024

    Passed: Building - Roof Decking

    Pull Missing Nails

    Inspected by Troy Crews

  10. Jun 24, 2024

    Cancelled: Building - Strapping

    Inspected by Troy Crews

  11. Jun 24, 2024

    Cancelled: Building - Framing

    Inspected by Troy Crews

  12. Jun 24, 2024

    Cancelled: Building - Rated Assembly Fastening

    Inspected by Troy Crews

  13. Jul 5, 2024

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Gary Pitzer

  14. Jul 5, 2024

    Passed: Building - Lath/Stucco

    Inspected by Gary Pitzer

  15. Jul 5, 2024

    Passed: Building - Framing

    Inspected by Gary Pitzer

  16. Jul 5, 2024

    Passed: Building - Fire Rated Wall

    No Fire Wall, Firestopping Only In Future This Will Be With Insulation Inspection

    Inspected by Gary Pitzer

  17. Jul 5, 2024

    Passed: Building - Insulation

    Vapor Barrier, Fire Stop

    Inspected by Gary Pitzer

  18. Jul 5, 2024

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Gary Pitzer

  19. Jul 5, 2024

    Passed: Mechanical - Rough In

    Inspected by Gary Pitzer

  20. Jul 29, 2024

    Failed: Electrical - Permanent Power

    Needs Disconnect On Exterior Of House

    Inspected by Gary Pitzer

  21. Jul 31, 2024

    Passed: Electrical - Permanent Power

    Changed Meter To Meter Disconnect Combo

    Inspected by Gary Pitzer

  22. Jul 31, 2024

    Release to power company

    Inspected by Gary Pitzer

  23. Sep 6, 2024

    Passed: Building - Final

    Cannot Closed Permit Or Release Certificate Of Occupancy Due To Missing Required Documents.

    Inspected by Gary Pitzer

  24. Sep 11, 2024

    Certificate-Release Certificate

    Inspected by Gary Pitzer

Documents