Permit Details

Permit Search

Permit

New Residential Construction

185 NE VEGAS TER
LAKE CITY, FL 32055

Permit #
000049732
Application #
65037
Status Completed
  1. Submitted Apr 24, 2024
  2. Issued May 6, 2024
  3. Expires Nov 23, 2025
  4. Completed May 27, 2025

Property

Parcel #
07310-008
Owner
Simmons James
Acres
0.44
Subdivision
—
Zoning
I
Flood zone
X
District
1

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0305D
This is the construction of a
Single Family Dwelling
Setbacks Front
20
Setback Side 1
15
Setback Side 2
15
Setbacks Rear
15
Stories
1
Heated Area (Sqft)
576
Total Area (Sqft)
576
Building Height
15
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
residential
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0347
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Sealed roof decking explanation for other option.
metal roofing
Service Amps
200

Status & Review History

  1. City of Lake City Utilities Notified.
  2. Point Review - Processing
  3. Zoning Review - Reviewed
  4. Plan Review - Plumbing Approved
  5. Plan Review - Mechanical Approved
  6. Plan Review - Electrical Approved
  7. Plan Review - Building Approved
  8. Plan Review - Reviewed
  9. Final Review - Documents Required
  10. Final Review - Documents Required
  11. Permit Issued
  12. Final Review - Complete

Contractors

This is an owner-builder project.

Inspections

  1. Jul 9, 2024

    Electrical -1st Underground Rough–In

    Footer Steel Bond

    Inspected by Gary Pitzer

  2. Jul 9, 2024

    Passed: Engineering - Setbacks

    Appears Ok From Info Provided

    Inspected by Gary Pitzer

  3. Jul 9, 2024

    Passed: Building - Footer

    2-#5 Rebar On Chairs, Trench Footers

    Inspected by Gary Pitzer

  4. Jul 30, 2024

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Dwv, And Water With +150 Psi, No Clean Out On Exterior

    Inspected by Gary Pitzer

  5. Aug 20, 2024

    Passed: Building - Slab

    Inspected by Troy Crews

  6. Sep 16, 2024

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  7. Sep 16, 2024

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  8. Dec 4, 2024

    Passed: Building - Framing

    Inspected by Troy Crews

  9. Dec 4, 2024

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  10. Dec 4, 2024

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  11. Dec 4, 2024

    Cancelled: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  12. Dec 4, 2024

    Cancelled: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  13. Dec 31, 2024

    Passed: Building - Insulation

    Inspected by Troy Crews

  14. Dec 31, 2024

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  15. Jan 10, 2025

    Septic Release Inspection

    Inspected by Health Dept

  16. Apr 15, 2025

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  17. Apr 15, 2025

    Release to power company

    Inspected by Troy Crews

  18. Apr 23, 2025

    Submitted Power Release through FPL Portal

    Inspected by Garber, Melissa

  19. May 20, 2025

    Failed: Building - Final

    Need To Check East Side Door Not Sealed Well, Also Need To Have Ac Operational.

    Inspected by Troy Crews

  20. May 27, 2025

    Certificate-Release Certificate

    Inspected by Troy Crews

  21. May 27, 2025

    Passed: Building - Final

    No Termite Final On Piers With Shields

    Inspected by Troy Crews