Permit Details

Permit Search

Permit

Solar Power System

502 NE REBECCA TER
LAKE CITY, FL 32055

Permit #
000049535
Application #
64654
Status Completed
  1. Submitted Mar 22, 2024
  2. Issued Apr 1, 2024
  3. Expires Oct 1, 2024
  4. Completed Apr 4, 2024

Property

Parcel #
04971-013
Owner
Mccombs Rockne, Mccombs Linda G
Acres
1.99
Subdivision
Double Run Acres
Zoning
RSF/MH-2
Flood zone
X
District
1

Permit

Status
Completed
Septic release
N/A
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0285D
PV Type
Stand Alone PV System without Batteries- (DC to AC without utility connection)
Grounding
N.E.C. Chapter 690
AC Options
Exposed
AC Options (Cont..)
In Conduit
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Power Company
Florida Power and Light
Residential or Commercial?
Residential
Where are the panels mounted?
Roof Mounted
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified.
  4. Point Review - Printed-Online Application
  5. Plan Review - Electrical Approved
  6. Plan Review - Building Approved
  7. Plan Review - Reviewed
  8. Zoning Review - Reviewed
  9. Final Review - Processing
  10. Final Review - Payment Needed
  11. Permit Issued

Contractors

  • Cameron Christensen

    Momentum Solar

    License
    CVC57036
    Title
    Cert. Solar
    Role
    Contractor
  • Matthew Franz

    Momentum Solar

    License
    EC13008217
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License Expired.

Inspections

  1. Apr 4, 2024

    Cancelled: Building - Footer

    Inspected by Anthony Aslan

  2. Apr 4, 2024

    Cancelled: Engineering - Setbacks

    Inspected by Anthony Aslan

  3. Apr 4, 2024

    Passed: Engineering - Access Road/Driveway Right-of-Way Integrity Inspection

    Exiting Driveway

    Inspected by Anthony Aslan

  4. Apr 4, 2024

    Passed: Solar - Solar Final

    Inspected by Anthony Aslan

  5. Apr 4, 2024

    Release to power company

    Inspected by Anthony Aslan

  6. Apr 4, 2024

    Passed: Electrical - Permanent Power

    Inspected by Anthony Aslan