Permit Details

Permit Search

Permit

New Residential Construction

259 NW LONA LOOP
LAKE CITY, FL 32055

Permit #
000048065
Application #
62190
Status Completed
  1. Submitted Aug 10, 2023
  2. Issued Jan 30, 2025
  3. Expires Mar 7, 2026
  4. Completed Sep 8, 2025

Property

Parcel #
02391-001
Owner
Metcalf Oliver Porter Jr, Metcalf Sonia Sue
Acres
1.73
Subdivision
Fairfield Woods
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0280D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
15'
Stories
1
Heated Area (Sqft)
796
Total Area (Sqft)
3301
Building Height
21
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
25-0525
If Other, explain the use of the structure.
This is for a SFR - Single Family Residence
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
Other (explain)
Sealed roof decking explanation for other option.
part of shell building
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Point Review - Reviewed
  5. Plan Review - Corrections Needed
  6. Plan Review - Documents Required
  7. Plan Review - Building Approved
  8. Plan Review - Electrical Approved
  9. Plan Review - Mechanical Approved
  10. Plan Review - Plumbing Approved
  11. Plan Review - Fuel/Gas Approved
  12. Plan Review - Reviewed
  13. Zoning Review - Reviewed
  14. Final Review - Reviewed
  15. Final Review - Payment Needed
  16. Permit Issued
  17. Permit Renewed
  18. Final Review - Complete
  19. Point Review - Reviewed
  20. Point Review - Reviewed
  21. Final Review - Payment Needed
  22. Final Review - Complete

Contractors

This is an owner-builder project.

Inspections

  1. Oct 23, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Electric Conduit Installed 4 Island 623 0168 Matt

    Inspected by Matt Forsyth

  2. Oct 31, 2023

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  3. Oct 31, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  4. Nov 7, 2023

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  5. Nov 7, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  6. Feb 2, 2024

    Passed: Building - Framing

    Exterior Metal Building Framing Complete

    Inspected by Matt Forsyth

  7. Jan 31, 2025

    Cancelled: Electrical - Permanent Power

    Inspected by Melissa Garber

  8. Feb 3, 2025

    Passed: Electrical - 1st Underground Rough–In

    Service Entrance Has Been Built

    Inspected by Matt Forsyth

  9. Feb 26, 2025

    Passed: Electrical - Temporary Service

    Inspected by Matt Forsyth

  10. Feb 26, 2025

    Release to power company

    Inspected by Matt Forsyth

  11. May 8, 2025

    Passed: Building - Framing

    Inspected by Matt Forsyth

  12. May 8, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  13. May 8, 2025

    Passed: Mechanical - Rough In

    Interior Exhaust Fan Duct Missing

    Inspected by Matt Forsyth

  14. May 8, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Nail Plates Missing On Vent Stack And Water Lines

    Inspected by Matt Forsyth

  15. May 13, 2025

    Passed: Building - Insulation

    Batts. Wall And Ceiling

    Inspected by Matt Forsyth

  16. Jun 17, 2025

    Passed: Electrical - Permanent Power

    Inspection Was From Meter Can Tobacco Dwelling 400 Meter Disconnect Too Many Garden Tools To Open Up The Service Panel No Branch Circuits In The Dwelling Have Been Run Yet Need Septic Release

    Inspected by Matt Forsyth

  17. Jun 18, 2025

    Passed: Electrical - Permanent Power

    Service Panel Inside Looks Good Will Need To Be Relabeled For Final Inspection-- Final Septic Release Required Prior To Release Of Power-- 6.19.25 Mg

    Inspected by Matt Forsyth

  18. Jul 1, 2025

    Release to power company

    Inspected by Melissa Garber

  19. Jul 1, 2025

    Septic Release Inspection

    Inspected by Health Dept

  20. Jul 1, 2025

    Submitted Power Release through FPL Portal

    Inspected by Garber, Melissa

  21. Aug 26, 2025

    Failed: Building - Final

    Final Termite Treatment Needed Outdoor Lights At Doors Need To Be Completed

    Inspected by Matt Forsyth

  22. Sep 5, 2025

    Passed: Building - Final

    Final Termite Treatment Received, Outdoor Light Wiring Has Been Secured-- All Requirements Met To Release Co 9.9.25 Mg

    Inspected by Troy Crews

  23. Sep 8, 2025

    Passed: Certificate - Release Certificate

    Re-release Of Co With Correct Spelling Of Name

    Inspected by Crews, Malcolm T.

Documents