| Septic Release Inspection |
|
Health Dept |
7/14/2023 |
| Passed: Building - Footer |
|
Troy Crews |
8/23/2023 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
8/23/2023 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
8/23/2023 |
| Passed: Building - Slab |
|
Anthony Aslan |
8/24/2023 |
| Cancelled: Building - Roof Decking |
|
Anthony Aslan |
9/29/2023 |
| Cancelled: Building - Wall Sheathing |
|
Anthony Aslan |
9/29/2023 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
10/2/2023 |
| Passed: Building - Wall Sheathing |
|
Anthony Aslan |
10/2/2023 |
| Passed: Building - Framing |
|
Anthony Aslan |
10/30/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
10/30/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
10/30/2023 |
| Failed: Mechanical - Rough In |
No Straps On Exhaust Venting, Duct Tape Is Not Allowed And Duct At That Location Is Not Allowed
no Gaskets On Supply And Return Drops
|
Anthony Aslan |
10/30/2023 |
| Passed: Mechanical - Rough In |
|
Anthony Aslan |
11/3/2023 |
| Passed: Building - Insulation |
|
Anthony Aslan |
11/3/2023 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
5/8/2024 |
| Release to power company |
|
Troy Crews |
5/8/2024 |
| Failed: Building - Final |
No Gas Connected
electrical Wires In Outside Panel
c/o's Paid
uv Insulation On A/c Lines
|
Anthony Aslan |
5/20/2024 |
| Passed: Building - Final |
Need Termite Final |
Anthony Aslan |
5/28/2024 |
| Certificate-Release Certificate |
Final Termite Recieved |
Troy Crews |
1/23/2025 |