Permit Details

Permit Search

Permit

Storage Building

4219 SE COUNTRY CLUB RD
LAKE CITY, FL 32025

Permit #
000047718
Application #
61427
Status Completed
  1. Submitted Jun 5, 2023
  2. Issued Dec 28, 2023
  3. Expires Feb 4, 2025
  4. Completed Aug 8, 2024

Property

Parcel #
08697-000
Owner
Windham John
Acres
9.95
Subdivision
—
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
ONE FOOT ABOVE ROAD
Fema map number
12023C0313D
Type of Structure
Storage Building
Commercial or Residential?
Commercial
Total Area (Sqft)
2500
Septic# (00-0000) or (X00-000)
23-0379
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setback Rear
10' (accessory)
Building Code Construction Type
III
Building Code Element
B
Building Code Occupancy Types
Business
Occupancy Use Title
mechanic shop
Dev Permit #
F023-
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Building Height
12
Building Length
50
Building Width
50
Service Amps
400

Status & Review History

  1. City of Lake City Notified of Application within Utility Service Areas LC_GAS, LC_WATER,.
  2. Point Review - Printed-Online Application
  3. Point Review - Printed-Online Application
  4. Point Review - Reviewed
  5. Plan Review - Plumbing Approved
  6. Plan Review - Electrical Approved
  7. Plan Review - Building Approved
  8. Plan Review - Reviewed
  9. Zoning Review - Documents Required
  10. Zoning Review - Documents Required
  11. Zoning Review - Documents Required
  12. Zoning Review - Documents Required
  13. Zoning Review - Reviewed
  14. Final Review - Processing
  15. Final Review - Processing
  16. Final Review - Reviewed
  17. Final Review - Payment Needed
  18. Permit Issued
  19. Permit Reissued

Contractors

This is an owner-builder project.

Inspections

  1. Sep 15, 2023

    Passed: Building - Monolithic Slab

    Inspected by Matt Forsyth

  2. Sep 15, 2023

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Mar 5, 2024

    Passed: Electrical - Permanent Power

    Need Septic Final For Release. Service Only Interior Wiring To Be Inspected At Final

    Inspected by Troy Crews

  4. Mar 6, 2024

    Septic Release Inspection

    Inspected by Health Dept

  5. Mar 7, 2024

    Release to power company

    Septic Released

    Inspected by Troy Crews

  6. May 10, 2024

    Passed: Building - Framing

    Inspected by Troy Crews

  7. May 10, 2024

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  8. May 10, 2024

    Release to power company

    Inspected by Troy Crews

  9. May 16, 2024

    Failed: Building - Final

    Not Ready For Final Need All Complete Including Handicapp Parking Spot And Site Work

    Inspected by Troy Crews

  10. May 16, 2024

    Passed: Building - Insulation

    Inspected by Troy Crews

  11. May 16, 2024

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  12. May 16, 2024

    Cancelled: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  13. Jul 30, 2024

    Failed: Building - Final

    Need Apron To Access Handicap Spot, Seal Holes In Wall For Ac Lines, Need Handrail On Other Side Of Stairs

    Inspected by Troy Crews

  14. Aug 4, 2024

    Passed: Fire - Fire Final

    Inspected by Cpt. Shane Overstreet

  15. Aug 8, 2024

    Passed: Building - Final

    Fire Final Done Items Corrected.

    Inspected by Troy Crews