Permit Details

Permit Search

Permit

New Commercial Construction

614 SE INDUSTRIAL PARK TER
LAKE CITY, FL 32055

Permit #
000047527
Application #
61073
Status Completed
  1. Submitted May 22, 2023
  2. Issued Jun 22, 2023
  3. Expires Aug 11, 2025
  4. Completed Feb 12, 2025

Property

Parcel #
10337-001
Owner
Columbia County, Florida
Acres
17.64
Subdivision
—
Zoning
MUD-I
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0320C
This is the construction of a:
Wastewater Treatment Plant
Driveway access to property:
Existing Drive
Is there a Fire Sprinkler System?
No
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setback Rear
25
Describe commercial use:
Wastewater Treatment Facility
Stories
1
Heated Area (Sqft)
750
Total Area (Sqft)
750
Building Height
12
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Utility & Misc
Occupancy Use Title
wastewater treatment plant and office
Dev Permit #
F023-
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Sealed roof decking options. (Must select one.)
N/A
Service Amps
1600

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified
  4. Point Review - Printed-Online Application
  5. Point Review - Reviewed
  6. Plan Review - Plumbing Approved
  7. Plan Review - Mechanical Approved
  8. Plan Review - Electrical Approved
  9. Plan Review - Building Approved
  10. Plan Review - Reviewed
  11. Zoning Review - Reviewed
  12. Final Review - Processing
  13. Final Review - Processing
  14. Permit Issued

Contractors

  • Timothy Smith

    Wharton-smith, Inc

    License
    CGC1511243
    Title
    Cert. General
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Chad Walker

    Cogburn Bros Inc

    License
    EC13008916
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Jul 13, 2023

    Passed: Building - Footer

    Chlorine Contact Bottom Slab

    Inspected by Troy Crews

  2. Jul 13, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Jul 13, 2023

    Passed: Building - Slab

    Inspected by Troy Crews

  4. Aug 3, 2023

    Passed: Building - Masonry Wall Reinforcing

    Formed Walls Of Tanks, First Lift.

    Inspected by Troy Crews

  5. Sep 21, 2023

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  6. Sep 21, 2023

    Release to power company

    Inspected by Troy Crews

  7. Oct 5, 2023

    Rescheduled 10/5/2023:Building - Slab

    Inspected by Troy Crews

  8. Oct 5, 2023

    Passed: Building - Slab

    Inspected by Troy Crews

  9. Oct 30, 2023

    Passed: Building - Slab

    Poured Wall At Chlorine Building.

    Inspected by Troy Crews

  10. Nov 8, 2023

    Passed: Building - Slab

    Electrical Room And Generator Slab

    Inspected by Troy Crews

  11. Nov 29, 2023

    Passed: Building - Masonry Wall Reinforcing

    Walls

    Inspected by Troy Crews

  12. Nov 29, 2023

    Passed: Building - Slab

    Tank Slabs

    Inspected by Troy Crews

  13. Dec 14, 2023

    Passed: Building - Masonry Wall Reinforcing

    Walls

    Inspected by Troy Crews

  14. Feb 21, 2024

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  15. Feb 21, 2024

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  16. Mar 22, 2024

    Passed: Building - Framing

    Inspected by Troy Crews

  17. Jul 16, 2024

    Passed: Building - Monolithic Slab

    Pictures Sent

    Inspected by Troy Crews

  18. Jul 16, 2024

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  19. Jul 16, 2024

    Passed: Electrical - 1st Underground Rough–In

    Pictures Sent

    Inspected by Troy Crews

  20. Jul 26, 2024

    Passed: Building - Monolithic Slab

    2 Slabs

    Inspected by Troy Crews

  21. Jul 26, 2024

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  22. Jul 26, 2024

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  23. Aug 9, 2024

    Passed: Building - Framing

    Contractor Had One Plate Left In Ceiling To Weld And Clean Up All Others

    Inspected by Troy Crews

  24. Sep 4, 2024

    Passed: Building - Insulation

    Inspected by Troy Crews

  25. Sep 4, 2024

    Passed: Building - Framing

    Inspected by Troy Crews

  26. Oct 24, 2024

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  27. Oct 24, 2024

    Release to power company

    Inspected by Troy Crews

  28. Feb 12, 2025

    Certificate-Release Certificate

    Inspected by Troy Crews

  29. Feb 12, 2025

    Passed: Building - Final

    Project Completed

    Inspected by Troy Crews