| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
6/15/2023 |
| Cancelled: Building - Slab |
|
Emaleigh Williams |
6/20/2023 |
| Failed: Building - Slab |
Clean Out Cave In Areas Complete Form Boards, Check With Architect About Transfers Bars Or Wire Chairs. |
Troy Crews |
6/20/2023 |
| Passed: Building - Roof Decking |
|
Troy Crews |
7/12/2023 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
7/12/2023 |
| Passed: Building - Framing |
Repair Cracked Truss North Porch Area |
Troy Crews |
7/28/2023 |
| Passed: Building - Roof Decking |
|
Troy Crews |
7/28/2023 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
7/28/2023 |
| Cancelled: Electrical - 1st Underground Rough–In |
|
Troy Crews |
7/28/2023 |
| Cancelled: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
7/28/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
7/28/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
7/28/2023 |
| Passed: Building - Insulation |
|
Troy Crews |
8/3/2023 |
| Cancelled: Building - Insulation |
|
Troy Crews |
8/4/2023 |
| Passed: Electrical - Permanent Power |
Need Final Septic Release |
Troy Crews |
9/19/2023 |
| Release to power company |
Rec'd Septic Final |
Troy Crews |
9/20/2023 |
| Septic Release Inspection |
|
Health Dept |
9/20/2023 |
| Rescheduled 11/21/2023:Building - Final |
|
Troy Crews |
11/17/2023 |
| Cancelled: Building - Final |
|
Troy Crews |
11/21/2023 |
| Passed: Building - Final |
|
Troy Crews |
12/1/2023 |