Permit Details

Permit Search

Permit

New Residential Construction

1724 SW HERLONG ST
FORT WHITE, FL 32038

Permit #
000047007
Application #
59056
Status Completed
  1. Submitted Mar 8, 2023
  2. Issued Apr 19, 2023
  3. Expires Jan 14, 2024
  4. Completed Jul 18, 2023

Property

Parcel #
09621-204
Owner
Blanchard Millard J, Blanchard Stephanie R
Acres
9.09
Subdivision
Tustenuggee Oaks Unr
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0485C
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
844
Total Area (Sqft)
912
Building Height
14
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
21-0811
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
Other (explain)
Service Amps
400

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Plan Review - Documents Required
  5. Plan Review - Documents Required
  6. Plan Review - Building Approved
  7. Plan Review - Electrical Approved
  8. Plan Review - Mechanical Approved
  9. Plan Review - Plumbing Approved
  10. Plan Review - Reviewed
  11. Zoning Review - Corrections Needed
  12. Zoning Review - Reviewed
  13. Final Review - Reviewed
  14. Final Review - Payment Needed
  15. Permit Issued

Contractors

This is an owner-builder project.

Inspections

  1. Mar 14, 2023

    Septic Release Inspection

    Inspected by Health Dept

  2. Apr 24, 2023

    Passed: Building - Wall Sheathing

    Inspected by Gary Pitzer

  3. Apr 24, 2023

    Cancelled: Building - Framing

    Inspected by Gary Pitzer

  4. Apr 24, 2023

    Cancelled: Building - Roof Decking

    Inspected by Gary Pitzer

  5. Apr 24, 2023

    Cancelled: Electrical - 1st Underground Rough–In

    Inspected by Gary Pitzer

  6. Apr 24, 2023

    Failed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  7. Apr 24, 2023

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Gary Pitzer

  8. Apr 24, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Gary Pitzer

  9. May 3, 2023

    Passed: Building - Framing

    Inspected by Gary Pitzer

  10. May 3, 2023

    Passed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  11. Jun 1, 2023

    Passed: Building - Insulation

    Inspected by Gary Pitzer

  12. Jul 18, 2023

    Passed: Building - Final

    Inspected by Gary Pitzer

Documents