| 3/31/2023 |
Application pending. |
| 3/31/2023 |
Application submitted by applicant. |
| 4/4/2023 |
Point Review - Printed-Online Application |
| 4/6/2023 |
Plan Review - Corrections Needed |
| 4/6/2023 |
Plan Review - Building Approved |
| 4/6/2023 |
Plan Review - Electrical Approved |
| 4/6/2023 |
Plan Review - Plumbing Approved |
| 4/6/2023 |
Plan Review - Reviewed |
| 4/10/2023 |
Zoning Review - Reviewed |
| 4/10/2023 |
Final Review - Documents Required |
| 4/11/2023 |
Plan Review - Reviewed |
| 4/12/2023 |
Final Review - Documents Required |
| 4/18/2023 |
Final Review - Reviewed |
| 4/18/2023 |
Final Review - Payment Needed |
| 4/19/2023 |
Permit Issued |