Permit Details

Permit Search

Permit

New Residential Construction

127 NW TREELINE GLN
LAKE CITY, FL 32055

Permit #
000046995
Application #
57257
Status Completed
  1. Submitted Mar 20, 2023
  2. Issued Apr 19, 2023
  3. Expires Jun 17, 2024
  4. Completed Dec 20, 2023

Property

Parcel #
02049-151
Owner
Widergren Todd E, Widergren Shelia
Acres
5.47
Subdivision
Rolling Oaks
Zoning
A-3
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0280D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
2101
Total Area (Sqft)
3283
Building Height
20
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
22-0934
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a self-adhering polymer-modified bitumen underlayment complying with ASTM D1970 applied over the entire roof.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Plan Review - Documents Required
  5. Plan Review - Building Approved
  6. Plan Review - Electrical Approved
  7. Plan Review - Mechanical Approved
  8. Plan Review - Plumbing Approved
  9. Plan Review - Fuel/Gas Approved
  10. Plan Review - Reviewed
  11. Zoning Review - Corrections Needed
  12. Zoning Review - Reviewed
  13. Final Review - Reviewed
  14. Final Review - Payment Needed
  15. Permit Issued
  16. Final Review - Payment Needed

Contractors

  • Mark Dawson

    Paradise Plumbing Services, Llc.

    License
    CFC1427245
    Title
    Plumbing Contractor
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Darin L Summerlin

    Summerlin Roofing Inc

    License
    CCC1326192
    Title
    Roofing Contractor
    Role
    Subcontractor
  • Donald Hollingsworth Ii

    Holly Elecreic Inc

    License
    EC13012104
    Title
    Cert. Electrical
    Role
    Subcontractor
  • Timothy D Shatto

    Shatto Heating & Air, Inc.

    License
    CAC057875
    Title
    A/c Class B
    Role
    Subcontractor

Inspections

  1. Mar 16, 2023

    Septic Release Inspection

    Inspected by Health Dept

  2. May 3, 2023

    Passed: Building - Footer

    Inspected by Matt Forsyth

  3. May 3, 2023

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  4. May 30, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Matt Forsyth

  5. May 30, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Matt Forsyth

  6. Jun 1, 2023

    Passed: Building - Slab

    Conduit Needed For Island

    Inspected by Matt Forsyth

  7. Jun 15, 2023

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  8. Jun 15, 2023

    Passed: Building - Ext Strapping/Wall Sheathing

    Carpenter Walked Around Job On Inspection, Talked About Attic Access For Framing Ins

    Inspected by Matt Forsyth

  9. Jun 20, 2023

    Passed: Building - Rated Assembly Fastening

    Inspected by Troy Crews

  10. Jun 28, 2023

    Passed: Building - Framing

    Back Sliding Door Not Installed

    Inspected by Matt Forsyth

  11. Jul 11, 2023

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  12. Jul 11, 2023

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  13. Jul 11, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Recommend Gas Lines Enclosed Wall Be Left Loose Not Stapled

    Inspected by Matt Forsyth

  14. Jul 18, 2023

    Passed: Building - Insulation

    Spray Foam

    Inspected by Matt Forsyth

  15. Dec 13, 2023

    Passed: Electrical - Permanent Power

    Need Blower Door Test For Final

    Inspected by Matt Forsyth

  16. Dec 13, 2023

    Release to power company

    Inspected by Matt Forsyth

  17. Dec 20, 2023

    Passed: Building - Final

    Inspected by Matt Forsyth

Documents