| Septic Release Inspection |
|
Health Dept |
3/14/2023 |
| Passed: Building - Footer |
|
Gary Pitzer |
3/21/2023 |
| Passed: Engineering - Setbacks |
Appears Ok Near Middle Of Lot |
Gary Pitzer |
3/21/2023 |
| Passed: Electrical - Temporary Service |
|
Gary Pitzer |
4/12/2023 |
| Release to power company |
|
Gary Pitzer |
4/12/2023 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Dvw Piping Pvc, Water Lines Cpvc With + 90 Psi ,no Gas, Also Under Slab Electric Conduit |
Gary Pitzer |
4/12/2023 |
| Passed: Building - Slab |
|
Gary Pitzer |
4/17/2023 |
| Release to power company |
|
Melissa Garber |
4/19/2023 |
| Passed: Building - Roof Decking |
|
Gary Pitzer |
5/9/2023 |
| Passed: Building - Wall Sheathing |
|
Gary Pitzer |
5/9/2023 |
| Passed: Building - Framing |
|
Troy Crews |
6/12/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
6/12/2023 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
6/12/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
6/12/2023 |
| Passed: Building - Insulation |
Roof Foamed And Walls Blown |
Gary Pitzer |
6/28/2023 |
| Passed: Electrical - Permanent Power |
|
Gary Pitzer |
10/16/2023 |
| Release to power company |
|
Gary Pitzer |
10/16/2023 |
| Passed: Building - Final |
|
Gary Pitzer |
11/13/2023 |