| Failed: Building - Footer |
Need Compaction Test, Permit Says No Plumbing, And Plumbing Installed |
Anthony Aslan |
4/24/2023 |
| Cancelled: Engineering - Setbacks |
|
Anthony Aslan |
4/24/2023 |
| Passed: Building - Footer |
|
Troy Crews |
4/25/2023 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
4/25/2023 |
| Passed: Electrical - Permanent Power |
Power For Storage Building Only. |
Troy Crews |
4/25/2023 |
| Passed: Electrical - Permanent Power |
Need Final Inspection From Enviromental Health For Release. |
Troy Crews |
6/14/2023 |
| Passed: Building - Final |
|
Troy Crews |
6/14/2023 |
| Release to power company |
|
Troy Crews |
7/11/2023 |
| Septic Release Inspection |
|
Health Dept |
8/7/2023 |