Permit Details

Permit Search

Permit

New Residential Construction

1316 SW MANDIBA DR
LAKE CITY, FL 32024

Permit #
000046634
Application #
58803
Status Completed
  1. Submitted Jan 24, 2023
  2. Issued Mar 2, 2023
  3. Expires Oct 29, 2024
  4. Completed May 2, 2024

Property

Parcel #
09280-160
Owner
Leech Martin John, Leech Alexandra
Acres
4.50
Subdivision
Oaks Of Lake City Phase 2
Zoning
PRRD
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Subdivision Plat
Finished floor requirement
77'
Requirement needed
By Nailing Inspection
Document needed is
a Surveyor letter giving the Finished Floor Elevation
Document receieved
Yes
Fema map number
12023C0395C
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
2
Heated Area (Sqft)
3480
Total Area (Sqft)
5842
Building Height
29.5
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
23-0028
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - On Hold-Incomplete
  4. Point Review - Printed-Online Application
  5. Plan Review - On Hold-Incomplete
  6. Plan Review - On Hold-Incomplete
  7. Plan Review - On Hold-Incomplete
  8. Plan Review - Corrections Needed
  9. Plan Review - Building Approved
  10. Plan Review - Electrical Approved
  11. Plan Review - Mechanical Approved
  12. Plan Review - Plumbing Approved
  13. Plan Review - Fuel/Gas Approved
  14. Plan Review - Reviewed
  15. Zoning Review - Reviewed
  16. Final Review - Reviewed
  17. Final Review - Reviewed
  18. Final Review - Payment Needed
  19. Permit Issued
  20. Final Review - Payment Needed

Contractors

  • Isaiah Cully

    Ic Construction Llc

    License
    CBC1259655
    Title
    Building Contractor
    Role
    Contractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Tyler M Turner

    Tmt Roofing Llc

    License
    CCC1330410
    Title
    Cert Roofing
    Role
    Subcontractor
  • Everton D Ruddock

    D&s Lighting Inc

    License
    EC13003800
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor

Inspections

  1. Mar 13, 2023

    Rescheduled 3/13/2023:Building - Footer

    Inspected by Gary Pitzer

  2. Mar 13, 2023

    Rescheduled 3/13/2023:Engineering - Setbacks

    Inspected by Gary Pitzer

  3. Mar 13, 2023

    Passed: Engineering - Setbacks

    Inspected by Gary Pitzer

  4. Mar 13, 2023

    Passed: Building - Footer

    Inspected by Gary Pitzer

  5. Mar 27, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    No Gas Or Electric , Under Slab Plumbing Only

    Inspected by Gary Pitzer

  6. Mar 28, 2023

    Passed: Building - Slab

    Inspected by Troy Crews

  7. Apr 4, 2023

    Passed: Electrical - Temporary Service

    Inspected by Gary Pitzer

  8. Apr 4, 2023

    Release to power company

    Inspected by Gary Pitzer

  9. Apr 25, 2023

    Passed: Building - Wall Sheathing

    Inspected by Gary Pitzer

  10. May 4, 2023

    Passed: Building - Roof Decking

    Partial Section Of Roof, South End Section Of Main Portion Of House, North Secfoon To Follow

    Inspected by Gary Pitzer

  11. May 25, 2023

    Passed: Building - Roof Decking

    Inspected by Gary Pitzer

  12. Aug 4, 2023

    Passed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  13. Aug 4, 2023

    Passed: Mechanical - Rough In

    Inspected by Gary Pitzer

  14. Aug 4, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Gary Pitzer

  15. Aug 4, 2023

    Failed: Building - Framing

    Steps Not To Code, First Step 7"1/2 , 2nd Step 8". Also Need Support Under Landing

    Inspected by Gary Pitzer

  16. Aug 15, 2023

    Building-Framing

    Stairs To Be Ok By Final With Floor Finish And Stair Tread Finish

    Inspected by Gary Pitzer

  17. Sep 29, 2023

    Passed: Building - Insulation

    Foam And Batts

    Inspected by Gary Pitzer

  18. Dec 4, 2023

    Septic Release Inspection

    Inspected by Health Dept

  19. Mar 6, 2024

    Passed: Electrical - Permanent Power

    Inspected by Gary Pitzer

  20. Mar 6, 2024

    Release to power company

    Inspected by Gary Pitzer

  21. May 1, 2024

    Rescheduled 5/2/2024:Building - Final

    Inspected by Troy Crews

  22. May 2, 2024

    Passed: Building - Final

    Inspected by Gary Pitzer

Documents