| Septic Release Inspection |
|
Health Dept |
1/26/2023 |
| Passed: Electrical - 1st Underground Rough–In |
This Was For Underground Plumbing |
Matt Forsyth |
1/30/2023 |
| Passed: Building - Monolithic Slab |
|
Troy Crews |
2/7/2023 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
2/7/2023 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
4/3/2023 |
| Passed: Building - Framing |
|
Troy Crews |
4/3/2023 |
| Passed: Building - Roof Decking |
|
Troy Crews |
4/3/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
4/3/2023 |
| Passed: Building - Final |
Cannot Closed Permit Or Release Certificate Of Occupancy Due To Missing Required Documents. |
Troy Crews |
2/7/2025 |