Swimming Pool and Spa
Permit
| Application #: | 57277 |
| Permit #: |
000046194 |
| Related Permit: |
|
| Submitted: | Tuesday, November 29, 2022 |
| Issued: | Tuesday, January 3, 2023 |
| Expires: | Friday, March 3, 2023 |
| Completed: | Friday, March 3, 2023 |
| Status: |
Completed |
| Septic Release? |
Yes |
Job Details
| Finished floor requirement |
|
| Fema map number |
12023C0382D |
| In floodway |
N |
| Is this for residential or commercial use? |
Residential |
| This is the construction of a: |
Pool |
| Setbacks Front |
30' |
| Setback Side 1 |
25' |
| Setbacks Rear |
200' buffer |
| Setback Side 2 |
25' |
| Building Code Edition |
2020 Florida Building Code 7th Edition and 2017 National Electrical Code |
| Septic# (00-0000) or (X00-000) |
22-0968 |
Review Notes
| 11/29/2022 |
Application pending. |
| 11/29/2022 |
Application submitted by applicant. |
| 11/29/2022 |
Point Review - Printed-Online Application |
| 11/29/2022 |
Plan Review - Reviewed |
| 12/1/2022 |
Zoning Review - Reviewed |
| 12/1/2022 |
Final Review - Documents Required |
| 12/2/2022 |
Final Review - Documents Required |
| 12/12/2022 |
Final Review - Reviewed |
| 12/12/2022 |
Final Review - Payment Needed |
| 1/3/2023 |
Permit Issued |
Contractors
| Name / Business |
License |
Title |
Role |
Chad Cunningham Peeler Pools Of North Florida Inc
|
CPC1459031 |
Cert. Residential Pool |
Contractor |
Matthew H Burns Burns Electrical Services Inc
|
EC13006531 |
Electrical Contractor |
Subcontractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Septic Release Inspection |
|
Health Dept |
12/13/2022 |
| Passed: Engineering - Setbacks |
Near Same Area Of House In Rear, Plenty Of Room To Rear Lot |
Gary Pitzer |
1/5/2023 |
| Passed: Swimming Pool - Pool Steel and Ground |
Rebar Installed With 4 Bonding Points And Tails |
Gary Pitzer |
1/5/2023 |
| Passed: Swimming Pool - Pool Deck/Piping Pressure |
|
Gary Pitzer |
1/17/2023 |
| Passed: Swimming Pool - Pool Footer |
|
Gary Pitzer |
1/17/2023 |
| Passed: Engineering - Setbacks |
|
Gary Pitzer |
1/17/2023 |
| Passed: Electrical - Pool/Deck Bonding |
Slab Bonds From Pool, Steel Footers Bonded, Long Tail To Future Equipment Location, Tail Out Backside Of Pool For Future Screen Room, Pressure And Footers Ok |
Gary Pitzer |
1/17/2023 |
| Cancelled: Swimming Pool - Pool Safety and Final |
|
Emaleigh Williams |
2/22/2023 |
| Passed: Swimming Pool - Pool Safety and Final |
Gate Unlocked And Doors Alarms Were Off But Were Functional. Owner Told That Alarms Were Suppose To Be Functional And Gate Locked All The Time |
Gary Pitzer |
3/3/2023 |