| Passed: Plumbing/Gas - 1st Underground Rough–In |
Plumbing Drain Only |
Gary Pitzer |
1/10/2023 |
| Passed: Building - Monolithic Slab |
Footer And Slab , Also Electric Under Slab |
Gary Pitzer |
1/23/2023 |
| Passed: Engineering - Setbacks |
|
Gary Pitzer |
1/23/2023 |
| Passed: Building - Wall Sheathing |
|
Gary Pitzer |
3/6/2023 |
| Septic Release Inspection |
|
Health Dept |
3/14/2023 |
| Passed: Building - Framing |
Trusses And Truss Bracing, Windows Screwed In And Sealed, Roof Nail Off Completed, Wall Nail Off Completed, |
Gary Pitzer |
4/28/2023 |
| Failed: Building - Roof Decking |
Metal Roofing End In Right Valley Not Seated Down |
Gary Pitzer |
7/28/2023 |
| Building-Roof Decking |
Metal Roofing Ajusted |
Gary Pitzer |
8/2/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Gary Pitzer |
10/24/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
10/24/2023 |
| Passed: Mechanical - Rough In |
|
Gary Pitzer |
1/16/2024 |
| Passed: Building - Insulation |
Foam In Walls |
Gary Pitzer |
3/5/2024 |
| Passed: Electrical - Permanent Power |
|
Gary Pitzer |
6/17/2024 |
| Release to power company |
|
Gary Pitzer |
6/17/2024 |
| Certificate-Release Certificate |
|
Gary Pitzer |
7/30/2024 |
| Passed: Building - Final |
|
Gary Pitzer |
7/30/2024 |