Permit Details

Permit Search

Permit

Storage Building

329 SW WILLIAM YOUNG LN
LAKE CITY, FL 32024

Permit #
000046006
Application #
57150
Status Completed
  1. Submitted Nov 15, 2022
  2. Issued Nov 30, 2022
  3. Expires Nov 29, 2023
  4. Completed Jun 2, 2023

Property

Parcel #
03578-005
Owner
Metzger Joseph J, Metzger Cheryl A
Acres
5.00
Subdivision
—
Zoning
A-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0379C
Type of Structure
Shed
Commercial or Residential?
Residential
Total Area (Sqft)
1050
Septic# (00-0000) or (X00-000)
22-0745
Setbacks Front
30
Setback Side 1
25
Setback Side 2
25
Setback Rear
25
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Storage
Occupancy Use Title
storage
Dev Permit #
F023-
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Building Height
15
Building Length
30
Building Width
35
Service Amps
200

Status & Review History

  1. Point Review - Received-Hard Copy Application
  2. Plan Review - Documents Required
  3. Plan Review - Documents Required
  4. Plan Review - Documents Required
  5. Plan Review - Plumbing Approved
  6. Plan Review - Electrical Approved
  7. Plan Review - Building Approved
  8. Plan Review - Reviewed
  9. Zoning Review - Reviewed
  10. Final Review - Reviewed
  11. Final Review - Reviewed
  12. Final Review - Payment Needed
  13. Permit Issued

Contractors

This is an owner-builder project.

Inspections

  1. Nov 16, 2022

    Septic Release Inspection

    Inspected by Health Dept

  2. Dec 5, 2022

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  3. Dec 6, 2022

    Cancelled: Building - Footer

    Inspected by Troy Crews

  4. Dec 6, 2022

    Cancelled: Engineering - Setbacks

    Inspected by Troy Crews

  5. Dec 8, 2022

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  6. Dec 8, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  7. Jan 3, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Interior Ri

    Inspected by Gary Pitzer

  8. Jan 3, 2023

    Passed: Electrical - 2nd Rough-In

    Interior Ri

    Inspected by Gary Pitzer

  9. Jan 24, 2023

    Passed: Building - Insulation

    Insulation

    Inspected by Gary Pitzer

  10. Jun 2, 2023

    Passed: Building - Final

    Inspected by Gary Pitzer