Permit Details

Permit Search

Permit

New Residential Construction

4474 SW COUNTY ROAD 18
FORT WHITE, FL 32038

Permit #
000045924
Application #
56628
Status Completed
  1. Submitted Sep 27, 2022
  2. Issued Nov 15, 2022
  3. Expires Aug 24, 2024
  4. Completed Feb 26, 2024

Property

Parcel #
04074-113
Owner
Dietel Rik E
Acres
4.99
Subdivision
Parker Woods
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0495C
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
2
Heated Area (Sqft)
3520
Total Area (Sqft)
9746
Building Height
26
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
22-0595
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
Other (explain)
Sealed roof decking explanation for other option.
24 ga tin on top of perlings

Status & Review History

  1. Point Review - Received-Hard Copy Application
  2. Point Review - Reviewed
  3. Plan Review - Corrections Needed
  4. Plan Review - Building Approved
  5. Plan Review - Electrical Approved
  6. Plan Review - Mechanical Approved
  7. Plan Review - Plumbing Approved
  8. Plan Review - Fuel/Gas Approved
  9. Plan Review - Reviewed
  10. Zoning Review - Reviewed
  11. Final Review - Documents Required
  12. Final Review - Corrections Needed
  13. Final Review - Reviewed
  14. Final Review - Payment Needed
  15. Permit Issued
  16. Final Review - Payment Needed

Contractors

  • Guy N Williams

    Slk Construction Inc

    License
    CBC050690
    Title
    Building Contractor
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

  • Donald R Hollingsworth

    Holly Electric Inc

    License
    EC13005429
    Title
    Electrical
    Role
    Subcontractor
  • Harry D Moseley Sr

    Harrys Heating & Air Conditioning Inc

    License
    RA0030316
    Title
    Class A A/c Contractor
    Role
    Subcontractor

    County License & State License Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Darin L Summerlin

    Summerlin Roofing Inc

    License
    CCC1326192
    Title
    Roofing Contractor
    Role
    Subcontractor

Inspections

  1. Oct 19, 2022

    Septic Release Inspection

    Inspected by Health Dept

  2. Nov 21, 2022

    Passed: Electrical - Temporary Service

    Inspected by Anthony Aslan

  3. Nov 21, 2022

    Release to power company

    Inspected by Anthony Aslan

  4. Dec 28, 2022

    Cancelled: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Emaleigh Williams

  5. Dec 28, 2022

    Cancelled: Electrical - 1st Underground Rough–In

    Inspected by Emaleigh Williams

  6. Dec 29, 2022

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Anthony Aslan

  7. Dec 29, 2022

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Anthony Aslan

  8. Jan 10, 2023

    Passed: Building - Footer

    Inspected by Anthony Aslan

  9. Jan 10, 2023

    Passed: Engineering - Setbacks

    Inspected by Anthony Aslan

  10. Jan 10, 2023

    Passed: Building - Monolithic Slab

    No Ground Wire Need Picture

    Inspected by Anthony Aslan

  11. Feb 9, 2023

    Cancelled: Building - Footer

    Already Passed Inspection

    Inspected by Emaleigh Williams

  12. Feb 9, 2023

    Cancelled: Engineering - Setbacks

    Already Passed Inspection

    Inspected by Emaleigh Williams

  13. Feb 9, 2023

    Cancelled: Building - Monolithic Slab

    Already Passed Inspection

    Inspected by Emaleigh Williams

  14. Feb 13, 2023

    Cancelled: Building - Footer

    Inspected by Emaleigh Williams

  15. Feb 13, 2023

    Cancelled: Engineering - Setbacks

    Inspected by Emaleigh Williams

  16. Feb 13, 2023

    Cancelled: Engineering - Setbacks

    Inspected by Melissa Garber

  17. Feb 13, 2023

    Cancelled: Building - Footer

    Inspected by Melissa Garber

  18. Feb 14, 2023

    Cancelled: Building - Footer

    Inspected by Anthony Aslan

  19. Feb 14, 2023

    Cancelled: Engineering - Setbacks

    Inspected by Anthony Aslan

  20. Feb 16, 2023

    Passed: Building - Footer

    Inspected by Anthony Aslan

  21. Feb 16, 2023

    Passed: Engineering - Setbacks

    Inspected by Anthony Aslan

  22. Aug 7, 2023

    Passed: Building - Framing

    Need Temporary Fall Protection On Stairs Inside stairs On Outside Of Build Needs A Hand Rail Installed.

    Inspected by Anthony Aslan

  23. Oct 17, 2023

    Passed: Electrical - 2nd Rough-In

    Inspected by Anthony Aslan

  24. Oct 17, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Anthony Aslan

  25. Oct 17, 2023

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Anthony Aslan

  26. Oct 17, 2023

    Failed: Mechanical - Rough In

    Fresh Air Needs To Be Insulated kitchen Exhaust Duct Can Not Be Reduced In Size, No Flex Pipe Allowed Must Be Smooth Inside multiple Ducts Kinked And Not Strapped have Question About Return For Down Stair System

    Inspected by Anthony Aslan

  27. Oct 19, 2023

    Passed: Mechanical - Rough In

    Need Straps On Supply Flex First Floor

    Inspected by Anthony Aslan

  28. Oct 26, 2023

    Passed: Building - Insulation

    Inspected by Anthony Aslan

  29. Jan 5, 2024

    Passed: Electrical - Permanent Power

    Inspected by Gary Pitzer

  30. Jan 5, 2024

    Release to power company

    Inspected by Gary Pitzer

  31. Feb 26, 2024

    Passed: Building - Final

    Inspected by Anthony Aslan

Documents