| 3/28/2022 |
Application pending. |
| 3/28/2022 |
Point Review - Processing |
| 4/7/2022 |
Point Review - Corrections Needed |
| 4/7/2022 |
Point Review - On Hold-Incomplete |
| 4/16/2022 |
Point Review - On Hold-Incomplete |
| 5/27/2022 |
Point Review - Printed-Online Application |
| 5/27/2022 |
Point Review - Reviewed |
| 6/2/2022 |
Plan Review - Corrections Needed |
| 6/3/2022 |
Zoning Review - Reviewed |
| 6/6/2022 |
Plan Review - Corrections Needed |
| 6/6/2022 |
Plan Review - Corrections Needed |
| 6/13/2022 |
Plan Review - Corrections Needed |
| 6/17/2022 |
Plan Review - Corrections Needed |
| 6/23/2022 |
Plan Review - Documents Required |
| 6/27/2022 |
Plan Review - Documents Required |
| 7/5/2022 |
Plan Review - Documents Required |
| 7/21/2022 |
Plan Review - Documents Required |
| 8/1/2022 |
Plan Review - Plumbing Approved |
| 8/1/2022 |
Plan Review - Mechanical Approved |
| 8/1/2022 |
Plan Review - Electrical Approved |
| 8/1/2022 |
Plan Review - Building Approved |
| 8/1/2022 |
Plan Review - Reviewed |
| 8/1/2022 |
Final Review - Documents Required |
| 8/3/2022 |
Final Review - Documents Required |
| 8/8/2022 |
Final Review - Documents Required |
| 8/15/2022 |
Final Review - Documents Required |
| 8/17/2022 |
Final Review - Documents Required |
| 8/17/2022 |
Final Review - Documents Required |
| 8/23/2022 |
Final Review - Reviewed |
| 8/26/2022 |
Final Review - Payment Needed |
| 10/3/2022 |
Permit Issued |
| 11/3/2022 |
Final Review - Payment Needed |
| 11/4/2022 |
Zoning Review - Reviewed |