| Passed: Building - Footer |
|
Troy Crews |
8/11/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
8/11/2022 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
8/29/2022 |
| Release to power company |
|
Troy Crews |
8/29/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
10/19/2022 |
| Passed: Building - Slab |
|
Troy Crews |
10/28/2022 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
12/16/2022 |
| Passed: Building - Roof Decking |
|
Troy Crews |
12/16/2022 |
| Passed: Building - Framing |
|
Troy Crews |
12/28/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
1/19/2023 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
1/19/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
1/19/2023 |
| Passed: Building - Insulation |
|
Troy Crews |
1/27/2023 |
| Passed: Electrical - Permanent Power |
Need Septic And Drive Finals |
Troy Crews |
4/13/2023 |
| Release to power company |
|
Melissa Garber |
4/28/2023 |
| Septic Release Inspection |
|
Health Dept |
4/28/2023 |
| Passed: Building - Final |
Driveway Good Per Blake 6/14/2023 |
Troy Crews |
6/14/2023 |