Permit Details

Permit Search

Permit

Mobile Home

260 NW DON HART WAY
WHITE SPRINGS, FL 32096

Permit #
000044893
Application #
54676
Status Completed
  1. Submitted May 5, 2022
  2. Issued Jul 6, 2022
  3. Expires Jun 13, 2023
  4. Completed Dec 27, 2022

Property

Parcel #
00079-008
Owner
Dempsey Robert K, Dempsey Kristal L
Acres
8.00
Subdivision
—
Zoning
A-3
Flood zone
0.2 PCT ANNUAL CHANCE FLOOD HAZARD
District
1

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0167D
In floodway
N
Mobile Home is a:
Double Wide
Year Built
2022
Width (Ft.In)
28
Length (Ft.In)
56
Driveway access to home:
Culvert Waiver
Installation Decal #
88497
Septic #
22-0392
Setbacks Front
30'
Setback Side 1
25'
Setbacks Rear
25'
Dev Permit #
F023-
Setback Side 2
25'
Are you applying for a 5 year temporary permit?
No
Serial #
jacfl37982ab
Wind Zone?
2
Residential or Commercial Use?
Residential
Service Amps
200

Status & Review History

  1. Point Review - Processing
  2. Point Review - Printed-Online Application
  3. Point Review - Reviewed
  4. Plan Review - Reviewed
  5. Zoning Review - Reviewed
  6. Final Review - Documents Required
  7. Final Review - Documents Required
  8. Final Review - Documents Required
  9. Final Review - Documents Required
  10. Final Review - Reviewed
  11. Final Review - Payment Needed
  12. Permit Issued

Contractors

  • Rusty L Knowles

    Floridas Finest Mobile Home Set Up

    License
    IH1038219
    Title
    Mh Installer (ih)
    Role
    Contractor
  • Glenn Whittington

    Whittington Electric Inc

    License
    EC13002957
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Michael A Boland

    Ace A/c Of Ocala Llc

    License
    CAC1817716
    Title
    Cert Class B A/c
    Role
    Subcontractor

Inspections

  1. Dec 15, 2022

    Passed: Mobile Home - Mobile Home Set-Up Final

    Need Septic Release

    Inspected by Matt Forsyth

  2. Dec 15, 2022

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Dec 27, 2022

    Release to power company

    Inspected by Melissa Garber

  4. Dec 27, 2022

    Certificate-Release Certificate

    Inspected by Matt Forsyth

  5. Dec 27, 2022

    Septic Release Inspection

    Inspected by Health Dept