Mobile Home
Permit
| Application #: | 54773 |
| Permit #: |
000044761 |
| Related Permit: |
|
| Submitted: | Wednesday, May 11, 2022 |
| Issued: | Friday, June 24, 2022 |
| Expires: | Friday, April 12, 2024 |
| Completed: | Friday, April 12, 2024 |
| Status: |
Completed |
| Septic Release? |
Yes |
Job Details
| Elevation regulation |
Minimum Requirement |
| Finished floor requirement |
One foot above the road |
| Fema map number |
12023C0415C |
| In floodway |
N |
| Mobile Home is a: |
Double Wide |
| Year Built |
2003 |
| Width (Ft.In) |
28 |
| Length (Ft.In) |
72 |
| Driveway access to home: |
Culvert Waiver |
| Installation Decal # |
29015 |
| Septic # |
22-0439 |
| Setbacks Front |
30' |
| Setback Side 1 |
25' |
| Setbacks Rear |
25' |
| Dev Permit # |
F023- |
| Setback Side 2 |
25' |
| Are you applying for a 5 year temporary permit? |
No |
| Serial # |
GMTD08166A/B |
| Wind Zone? |
2 |
| Residential or Commercial Use? |
Residential |
Review Notes
| 5/11/2022 |
Point Review - Processing |
| 5/17/2022 |
Point Review - Printed-Online Application |
| 5/17/2022 |
Point Review - Reviewed |
| 5/18/2022 |
Plan Review - Reviewed |
| 5/18/2022 |
Zoning Review - Reviewed |
| 5/19/2022 |
Final Review - Documents Required |
| 5/23/2022 |
Final Review - Documents Required |
| 5/23/2022 |
Final Review - Documents Required |
| 6/3/2022 |
Final Review - Documents Required |
| 6/6/2022 |
Final Review - Documents Required |
| 6/9/2022 |
Final Review - Documents Required |
| 6/13/2022 |
Final Review - Documents Required |
| 6/13/2022 |
Final Review - Documents Required |
| 6/17/2022 |
Final Review - Reviewed |
| 6/17/2022 |
Final Review - Contact the Building Dept |
| 6/22/2022 |
Final Review - Payment Needed |
| 6/22/2022 |
Permit Issued |
| 6/24/2022 |
Final Review - Payment Needed |
| 6/24/2022 |
Permit Reissued |
Contractors
| Name / Business |
License |
Title |
Role |
Manuel M Brannan Mikes Mobile Setup Llc
|
IH1025396 |
Mh Installer (ih) |
Contractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Passed: Mobile Home - In County Pre-Mobile Home before set-up |
|
Anthony Aslan |
6/22/2022 |
| Septic Release Inspection |
|
Health Dept |
8/12/2022 |
| Passed: Engineering - Setbacks |
|
Gary Pitzer |
4/21/2023 |
| Passed: Mobile Home - Mobile Home Set-Up Final |
Owner Owes Us A Couple Pictures When Clay Electric Completes The Service Installation |
Gary Pitzer |
4/21/2023 |
| Release to power company |
|
Gary Pitzer |
4/21/2023 |
| Certificate-Release Certificate |
|
Troy Crews |
4/12/2024 |