| Application #: | 54344 |
| Permit #: |
000044680 |
| Related Permit: |
|
| Submitted: | Tuesday, April 12, 2022 |
| Issued: | Tuesday, June 14, 2022 |
| Expires: | Wednesday, October 12, 2022 |
| Completed: | Wednesday, October 12, 2022 |
| Status: |
Completed |
| Septic Release? |
N/A |
Notes
SE0631 NEW CELL TOWER
| Finished floor requirement |
|
| Fema map number |
12023C0305D |
| This is the construction of a: |
305ft Self Support Tower |
| Select access to property: |
Culvert Permit |
| Total Estimated Cost |
250000 |
| Tower Height |
305 |
| Building Code Edition |
2020 Florida Building Code 7th Edition and 2017 National Electrical Code |
| Is this a new or existing tower? |
New |
| Service Amps |
800 |
| 4/12/2022 |
Application pending. |
| 4/12/2022 |
Point Review - Processing |
| 4/15/2022 |
Point Review - On Hold-Incomplete |
| 5/6/2022 |
Plan Review - Corrections Needed |
| 5/13/2022 |
Plan Review - Corrections Needed |
| 5/16/2022 |
Plan Review - Corrections Needed |
| 5/19/2022 |
Plan Review - Documents Required |
| 5/23/2022 |
Plan Review - Documents Required |
| 6/3/2022 |
Plan Review - Documents Required |
| 6/6/2022 |
Plan Review - Documents Required |
| 6/9/2022 |
Plan Review - Documents Required |
| 6/13/2022 |
Plan Review - Documents Required |
| 6/14/2022 |
Plan Review - Electrical Approved |
| 6/14/2022 |
Plan Review - Building Approved |
| 6/14/2022 |
Plan Review - Reviewed |
| 6/14/2022 |
Zoning Review - Reviewed |
| 6/14/2022 |
Final Review - Reviewed |
| 6/14/2022 |
Point Review - Reviewed |
| 6/14/2022 |
Permit Issued |
| Name / Business |
License |
Title |
Role |
Kenneth Harbour Cleveland Mechanical
County License & State License & Liability Insurance & Workers Comp Expired. |
CGC1520767 |
Cert. General |
Contractor |
John Cleveland Cleveland Mechanical
County License & State License & Liability Insurance & Workers Comp Expired. |
EC0001621 |
Cert. Electrical |
Subcontractor |
| Inspection |
Notes |
Performed By |
Date |
| Passed: Building - Footer |
1 St Hole |
Troy Crews |
8/11/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
8/11/2022 |
| Passed: Building - Footer |
2 Nd Hole |
Troy Crews |
8/16/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
8/16/2022 |
| Passed: Building - Footer |
3 Rd Hole |
Troy Crews |
8/18/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
8/18/2022 |
| Passed: Electrical - 1st Underground Rough–In |
Ground Ring And Conduits For Service |
Troy Crews |
9/1/2022 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
9/20/2022 |
| Release to power company |
|
Troy Crews |
9/20/2022 |
| Release to power company |
Changed From Clay To Fpl |
Melissa Garber |
9/21/2022 |
| Passed: Building - Footer |
Looked At During Final Power |
Troy Crews |
9/26/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
9/26/2022 |
| Passed: Building - Slab |
|
Troy Crews |
9/26/2022 |
| Failed: Building - Final |
Now Power Meter Set And Slabs Not Poured. |
Troy Crews |
10/6/2022 |
| Passed: Building - Final |
Tower Job Only Generator And Co Location To Follow |
Troy Crews |
10/12/2022 |