Permit Details

Permit Search

Permit

New Residential Construction

162 NW CREWS GLN
LAKE CITY, FL 32055

Permit #
000044529
Application #
54586
Status Completed
  1. Submitted Apr 29, 2022
  2. Issued May 25, 2022
  3. Expires Jul 4, 2023
  4. Completed Jan 18, 2023

Property

Parcel #
01901-001
Owner
Jorge Yasmanis Reyes, Lobana Daymara Velazquez
Acres
7.62
Subdivision
—
Zoning
A-3
Flood zone
X
District
1

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0195D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
1810
Total Area (Sqft)
2362
Building Height
17
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
22-0171
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Point Review - Received-Hard Copy Application
  2. Point Review - Reviewed
  3. Plan Review - Documents Required
  4. Zoning Review - Reviewed
  5. Plan Review - Documents Required
  6. Plan Review - Building Approved
  7. Plan Review - Electrical Approved
  8. Plan Review - Mechanical Approved
  9. Plan Review - Plumbing Approved
  10. Plan Review - Reviewed
  11. Final Review - Reviewed
  12. Final Review - Payment Needed
  13. Permit Issued
  14. Final Review - Payment Needed

Contractors

This is an owner-builder project.

Inspections

  1. Jun 10, 2022

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Anthony Aslan

  2. Jun 14, 2022

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  3. Jun 14, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  4. Jun 28, 2022

    Passed: Building - Lintel/Tie Beam

    Inspected by Troy Crews

  5. Jun 28, 2022

    Passed: Building - Masonry Wall Reinforcing

    Inspected by Troy Crews

  6. Jun 28, 2022

    Passed: Building - Vertical Cells/Columns

    Inspected by Troy Crews

  7. Jul 15, 2022

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  8. Jul 15, 2022

    Passed: Building - Framing

    Roof Trusses

    Inspected by Troy Crews

  9. Jul 15, 2022

    Passed: Building - Strapping

    Inspected by Troy Crews

  10. Aug 19, 2022

    Septic Release Inspection

    Inspected by Health Dept

  11. Aug 22, 2022

    Rescheduled 8/23/2022:Building - Framing

    Inspected by Emaleigh Williams

  12. Aug 22, 2022

    Rescheduled 8/23/2022:Electrical - 2nd Rough-In

    Inspected by Emaleigh Williams

  13. Aug 22, 2022

    Rescheduled 8/23/2022:Mechanical - Rough In

    Inspected by Emaleigh Williams

  14. Aug 22, 2022

    Rescheduled 8/23/2022:Plumbing/Gas - 2nd Rough-In

    Inspected by Emaleigh Williams

  15. Aug 22, 2022

    Rescheduled 8/23/2022:Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Emaleigh Williams

  16. Aug 23, 2022

    Passed: Building - Framing

    Inspected by Troy Crews

  17. Aug 23, 2022

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  18. Aug 23, 2022

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  19. Aug 23, 2022

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  20. Aug 30, 2022

    Passed: Building - Insulation

    Inspected by Troy Crews

  21. Oct 11, 2022

    Cancelled: Electrical - Permanent Power

    Inspected by Troy Crews

  22. Oct 11, 2022

    Passed: Electrical - 1st Underground Rough–In

    Conduit From House To Power Pole

    Inspected by Troy Crews

  23. Nov 7, 2022

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  24. Nov 7, 2022

    Release to power company

    Inspected by Troy Crews

  25. Jan 5, 2023

    Passed: Building - Final

    Need Blower Door And Final Termite

    Inspected by Troy Crews

  26. Jan 18, 2023

    Certificate-Release Certificate

    Blower Door And Final Termite Received

    Inspected by Troy Crews