| Passed: Building - Footer |
|
Matt Forsyth |
5/11/2022 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
5/11/2022 |
| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
5/25/2022 |
| Release to power company |
|
Matt Forsyth |
5/25/2022 |
| Passed: Building - Slab |
|
Matt Forsyth |
5/27/2022 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
7/12/2022 |
| Passed: Building - Framing |
|
Matt Forsyth |
7/12/2022 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
7/12/2022 |
| Passed: Building - Strapping |
|
Matt Forsyth |
7/12/2022 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
7/12/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
8/5/2022 |
| Passed: Mechanical - Rough In |
Nice Job |
Matt Forsyth |
8/5/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
8/5/2022 |
| Passed: Building - Insulation |
Walls Only |
Matt Forsyth |
8/18/2022 |
| Passed: Electrical - Permanent Power |
Need Septic Released |
Matt Forsyth |
10/10/2022 |
| Release to power company |
|
Melissa Garber |
10/13/2022 |
| Septic Release Inspection |
|
Health Dept |
10/13/2022 |
| Cancelled: Electrical - Permanent Power |
|
Matt Forsyth |
10/13/2022 |
| Failed: Building - Final |
Hot Water Heater Piped To Outside Blower Door And Final Termite Needed For Final |
Matt Forsyth |
11/18/2022 |
| Certificate-Release Certificate |
Blower Door , Termite, And Drain Line Completed |
Troy Crews |
11/23/2022 |
| (Requested) Plumbing/Gas-1st Underground Rough–In |
|
|
|